Before you start
Installation workflows
1 Before you start
Read this chapter carefully before you begin the installation.
This chapter includes:
•Installation workflows
•Gathering information
•Unpacking
•Site requirements
•Required equipment
Installation workflows
You can use this guide to help perform any of the following:
•a full installation — in which the G350 is shipped to the customer site with no media modules installed and not configured.
•a staging — in which you install media modules and have a supporting technician configure the G350 before shipping it to the customer site.
•an installation of a staged G350 — in which you receive the G350 after staging. The G350 has the media modules already installed and is already configured.
Full installation
If you are performing the entire installation at the customer site, work through the guide from beginning to end. The workflow is as follows:
•Mount the G350, install the required media modules in the G350, install ground conductors, and connect power to the G350 (Chapter 2, “Installing the Avaya G350 Media Gateway”).
•Prepare the G350 to be configured by a supporting technician (Chapter 3, “Preparing for configuration”).
•Connect endpoint devices, such as telephones, LAN and WAN computers, to the G350 and collaborate with a supporting technician who configures the G350 (Chapter 4, “Connecting devices”).
•Test the installation and remove the installation equipment (Chapter 5, “After installation”).
Installation of the G350 Media Gateway | 13 |
December 2003 |
|