APC 9000 installation manual Installation with parallel frequency converters

Page 8

Characteristics

The table below serves as an example for an installation comprising up to four frequency converters or four parallel UPSs with a centralised SSC.

– for installations with redundant units, take into account only the units required to supply the load power

(e.g. for an installation made up of 3 parallel-connected rectifier-inverter cubicles, one being redundant, only 2 rectifier- inverter cubicles are used to determine Mains 2 and load currents and cable cross-sections);

this table has been drawn up for rated phase-to-phase Mains 2 and load voltages of 415 V and full rated load with a power factor of 0.9. For voltages of 380 or 400 V, multiply the indicated currents by 1.09 and 1.04 respectively, then modify the cable cross-sections accordingly if necessary.

The cable cross-sections in this table are for the parts illustrated in bold on the following block diagrams (installation examples, figures 1 and 2).

Parameters for Mains 2 and load cables for an installation comprising frequency converters or parallel UPSs with a centralised SSC.

rated

number of

total UPS

Mains 2 or load

cable

inverter

parallel-connected

rated output

line current

cross-section (1)

output

inverters

in kVA

in Amps

in mm²

in kVA

 

 

 

 

 

 

 

 

 

800

2

1600

2310

Please consult us*

 

3

2400

3465

Please consult us*

 

4

3200

4620

Please consult us*

 

 

 

 

 

900

2

1800

2598

Please consult us*

 

3

2700

3897

Please consult us*

 

4

3600

5196

Please consult us*

 

 

 

 

 

(1) cable cross-sections are given for copper conductors of the U1000 R02V type (increase by 30 % for aluminium conductors). They are calculated according to permissible temperature rise and allow for line voltage drops over a maximum length of 100 m. For greater lengths, the cross-sections should be chosen to limit voltage drops to 3 %.

* NF C 15-100 authorizes a maximum of 4 cables per phase.

Installation with parallel frequency converters I

mains 1

inverter 1

mains 1

inverter 2

load

mains 1

inverter 3

Fig. 1

Installation with parallel UPSs with a centralised SSC

mains 2

mains 1

mains 1

inverter 1

inverter 2

static switch cubicle

load

mains 1

inverter 3

Fig. 2

34006451EN/AC - Page 8

Image 8
Contents Installation manual Mgetm GalaxyTM34006451EN/AC Contents Characteristics Characteristics common to all cubiclesStatic Switch Cubicle Characteristics of rectifier-inverter cubiclesCharacteristics of Static Switch Cubicles Rectifier-inverter cubicleElectrical parameters for selecting protective devices Electrical parameters for MainsElectrical parameters for Mains 2 415 Rated Mains 1 current InverterElectrical parameters for determining cable cross-sections Parameters for single-unit UPS cablesNF C 15-100 authorizes a maximum of 4 cables per phase Installation with parallel frequency convertersInstallation with parallel UPSs with a centralised SSC Maintenance Bypass cubicle Mains Inverter Mains 1 mains Load Handing Positioning the cubiclesSide clearances provided by the spacing uprights Rear FrontFloor loads figure Cubicle layout on false floor or normal floor figures 6, 7Cubicle footpads Rear Connection via the bottomLayout for a single-unit UPS with one battery cubicle Rear Special case Power circuit wiring diagramsDiagram for a frequency converter with batteries Diagram for a frequency converter without batteries Example of a 2 parallel UPS rectifier-inverters with SSCModular UPS cubicle External maintenance bypass cubicle Cubicle mounting and connection Mounting of the left and right cubiclesXFGD06 Internal connections between cubiclesXMGD05 Connection of power circuits GeneralLeft cubicle of single-unit or parallel UPS with SSC Cross-section AARight cubicle of single-unit UPS XR1 XR8XR9 XR2 XR5 XR3 XR6 XR4 XR7Right cubicle of a parallel UPS with SSC Front RearXR2 XR5 XR3 XR6 XR4 XR7Connection of auxiliary circuits on the remote relay board XR1 XR2 XR3 XR4Connection to battery circuit breaker QF1 Emergency shutdownConnections between Apoz boards Connections between rectifier-inverter cubiclesXM XM XM XM UPS Connections between Misi boards modular UPSsMisi Misi Acpz board of the Static Switch Cubicle XR8 XR9 XR5 XR6 XR7XR2 XR1 Connection of the battery Temperature Monitor optionalConnections Dimensions of the Temperature Monitor 75 x 75 x 21 mm Temperature Monitor installation in a battery roomTemperature Monitor base Final installation steps Connection of the LED remote indications unitMains 2 line protection Rated inverter output kVA Maximum permissible currentCubicle mounting Left cubicleQ4S XF1-XF2 XM1-XM2Right cubicle of a 2000 kVA Static Switch Front viewRear Front view Left cubicle of a 2000 kVA Static SwitchFront 120 to 1200 kVA Static Switch Cubicles Details of earthing connections in the various cubiclesRectifier-inverter cubicle Inverter InputComz KVA Static Switch CubiclesTele-Monitor unit 34006451EN/AC 34006451EN/AC 34006451EN/AC 34006451EN/AC