Characteristics

The table below serves as an example for an installation with up to four modular UPSs with an external maintenance bypass.

– for installations with redundant units, take into account only the units required to supply the load power

(e.g. for an installation made up of 3 parallel-connected rectifier-inverter cubicles, one being redundant, only 2 units are used to determine the currents on the maintenance bypass line and the load, and the cross-sectional areas of cables);

this table has been drawn up for rated phase-to-phase Mains 2 and load voltages of 415 V and full rated load with a power factor of 0.9. For voltages of 380 or 400 V, multiply the indicated currents by 1.09 and 1.04 respectively, then modify the cable cross-sections accordingly if necessary.

The cable cross-sections in this table are for the parts illustrated in bold on the following block diagrams (installation example, figure 3);

important. In an installation with an external maintenance bypass, the power cables between each UPS and the upstream protection devices must be the same length. The same holds for the power cables between each UPS cubicle and the external maintenance bypass.

rated

number of

total UPS

mains 2 or load

cable

inverter

parallel-connected

rated output

line current

cross-section (1)

output

inverters

in kVA

in Amps

in mm²

in kVA

 

 

 

 

 

 

 

 

 

800

2

1600

2310

Please consult us*

 

3

2400

3465

Please consult us*

 

4

3200

4620

Please consult us*

 

 

 

 

 

900

2

1800

2598

Please consult us*

 

3

2700

3897

Please consult us*

 

4

3600

5196

Please consult us*

 

 

 

 

 

(1) cable cross-sections are given for copper conductors of the U1000 R02V type (increase by 30 % for aluminium conductors). They are calculated according to permissible temperature rise and allow for line voltage drops over a maximum length of 100 m. For greater lengths, the cross-sections should be chosen to limit voltage drops to 3 %.

* NF C 15-100 authorizes a maximum of 4 cables per phase.

Installation comprising modular UPSs with an external maintenance bypass

maintenance Bypass cubicle

mains 1

inverter 1

 

mains 2

 

mains 1 mains 2

inverter 2

load

mains 1 mains 2

inverter 3

Fig. 3

34006451EN/AC - Page 9

Image 9
Contents Mgetm GalaxyTM Installation manual34006451EN/AC Contents Characteristics common to all cubicles CharacteristicsCharacteristics of rectifier-inverter cubicles Static Switch CubicleCharacteristics of Static Switch Cubicles Rectifier-inverter cubicleElectrical parameters for Mains Electrical parameters for selecting protective devicesElectrical parameters for Mains 2 415 Rated Mains 1 current InverterParameters for single-unit UPS cables Electrical parameters for determining cable cross-sectionsInstallation with parallel frequency converters Installation with parallel UPSs with a centralised SSCNF C 15-100 authorizes a maximum of 4 cables per phase Maintenance Bypass cubicle Mains Inverter Mains 1 mains Load Positioning the cubicles HandingSide clearances provided by the spacing uprights Rear FrontCubicle layout on false floor or normal floor figures 6, 7 Floor loads figureCubicle footpads Rear Connection via the bottomLayout for a single-unit UPS with one battery cubicle Rear Power circuit wiring diagrams Diagram for a frequency converter with batteriesSpecial case Example of a 2 parallel UPS rectifier-inverters with SSC Diagram for a frequency converter without batteriesModular UPS cubicle External maintenance bypass cubicle Mounting of the left and right cubicles Cubicle mounting and connectionInternal connections between cubicles XMGD05XFGD06 General Connection of power circuitsLeft cubicle of single-unit or parallel UPS with SSC Cross-section AAXR1 XR8 Right cubicle of single-unit UPSXR9 XR2 XR5 XR3 XR6 XR4 XR7Front Rear Right cubicle of a parallel UPS with SSCXR2 XR5 XR3 XR6 XR4 XR7XR1 XR2 XR3 XR4 Connection of auxiliary circuits on the remote relay boardEmergency shutdown Connection to battery circuit breaker QF1Connections between Apoz boards Connections between rectifier-inverter cubiclesXM XM XM XM Connections between Misi boards modular UPSs MisiUPS Misi XR8 XR9 XR5 XR6 XR7 Acpz board of the Static Switch CubicleConnection of the battery Temperature Monitor optional ConnectionsXR2 XR1 Temperature Monitor installation in a battery room Temperature Monitor baseDimensions of the Temperature Monitor 75 x 75 x 21 mm Connection of the LED remote indications unit Final installation stepsRated inverter output kVA Maximum permissible current Mains 2 line protectionLeft cubicle Cubicle mountingQ4S XF1-XF2 XM1-XM2Front view Right cubicle of a 2000 kVA Static SwitchLeft cubicle of a 2000 kVA Static Switch FrontRear Front view Details of earthing connections in the various cubicles 120 to 1200 kVA Static Switch CubiclesRectifier-inverter cubicle Inverter InputKVA Static Switch Cubicles Tele-Monitor unitComz 34006451EN/AC 34006451EN/AC 34006451EN/AC 34006451EN/AC