Operation – Operation Procedures
Note
Restart – single system with MBP.
Only trained personnel familiar with the construction and the equipment may
restart the UPS.
Warning
From the XR Enclosure(s) (if available): Connect the batteries by pushing them in.
From the XR Enclosure(s) (if available): Set the DC disconnect switch (if available) to the ON position.
From the external MBP: Turn the output switch (Q002) to position “I” (ON).
Check that the load is ON.
The UPS is now ready to support the load.
From the UPS: Connect the batteries by pushing them in.
From the external MBP: Turn the input switch (Q001) to position “1” (ON).
From the UPS: Turn load ON from the display via Control – Turn Load on – Yes, turn Load on.
Note
Note