Maintenance – Parts Replacement

Follow the below procedures if you need to change or add a battery module, e.g. if you receive a display

message reporting a bad battery, or if you need to add batteries for increased runtime.

XRUPS

When removing Battery Modules, start from

Holding the battery handle, gently push the

the highest level and work down.

battery upwards and pull it halfway out of

 

the enclosure. A lock mechanism prevents it

 

from being pulled all the way out.

To release the battery from the lock

 

mechanism, gently push the battery upwards

 

again and pull it out, while another person

 

supports the battery.

 

Installation. If additional batteries are needed for extra runtime, or if you install battery replacement modules, be aware of the following:

Caution

Caution

Batteries must be replaced by trained personnel only (see the section General safety prior to Battery Module replacement).

Do not install Battery Modules in the UPS until you are ready to power up the system. Disregarding this caution can result in a deep discharge of the batteries and cause permanent damage. The time between battery installation and powering up the UPS should not exceed 72 hours or 3 days.

990-2282A-001

Smart-UPS® VT 10-40 kVA 400V, 208V, 200V – Operation

31

Image 37
Contents Operation Page Companion manuals About this ManualHow to find updates to this manual Contents Maintenance Safety User Interface OverviewInterface area Display interfaceMain Menu Screen Menu tree Previous screens Operation Modes OperationHow to turn into bypass Operation ProceduresSingle System turning into external bypass Parallel System turning into external bypass Control-UPS out of bypass-Yes, UPS out of bypass How to turn into normal operationEach display via Control-Turn Load on How to turn load OFF/ON via the display interface Use the UP/DOWN keys to go through the parameters How to view the Status screensHow to view Logging and Statistics Diags. View troubleshooting information How to use the Diags screenTurn Load Off How to perform a total power offLoad off-Yes, turn Load off Total power off isolating one UPS in a parallel system How to perform a restart Restart single system with MBP Load on- Yes, turn Load on Settings ConfigurationHow to change the Clock and the Alarms in the Setting menu  To go to Time Configuration Settings Parts Replacement MaintenanceHow to determine if you need a replacement part How to return parts to APCReplaceable parts only trained personnel How to store the battery modulesUser interface front How to replace and install a battery module How to replace a Network Management Card24 kg / 4 x 53 lbs   Xrups UPS / XR Status and Alarm Messages TroubleshootingDisplay messages Troubleshooting Status and Alarm Messages See the section How to replace Display Message Meaning Corrective Action Page 990-2282A-001 APC Worldwide Customer Support01/2007