APC VT manual Load on- Yes, turn Load on

Page 27

Operation – Operation Procedures

Restart – parallel system.

Only trained personnel familiar with the construction and the equipment may

restart the UPS system.

Warning

From the XR Enclosure(s) (if available): Connect the batteries on the UPS units by pushing them in.

From the XR Enclosure(s) (if available): Set the DC disconnect switch (if available) to the ON position.

From the external MBP: Turn all output switches (Q002) to position “1” (ON).

From the UPS: Turn load ON each of the UPS units from the display via Control Turn

Load onYes, turn Load on.

From the UPS: Connect the batteries by pushing them in.

From the external MBP: Turn all input switches (Q001) to position “1” (ON).

From the external MBP: Turn the output isolation breaker (Q004) to position “1” (ON).

Check that the load is ON.

The UPS system is now ready to support the load.

Note

Auto-detection on frequency – if a problem occurs call APC Customer Support (see the back cover of this manual).

Note

990-2282A-001

Smart-UPS® VT 10-40 kVA 400V, 208V, 200V – Operation

21

Image 27
Contents Operation Page Companion manuals About this ManualHow to find updates to this manual Contents Maintenance Safety Display interface OverviewUser Interface Interface areaMain Menu Screen Menu tree Previous screens Operation Modes OperationHow to turn into bypass Operation ProceduresSingle System turning into external bypass Parallel System turning into external bypass Control-UPS out of bypass-Yes, UPS out of bypass How to turn into normal operationEach display via Control-Turn Load on How to turn load OFF/ON via the display interface Use the UP/DOWN keys to go through the parameters How to view the Status screensHow to view Logging and Statistics Diags. View troubleshooting information How to use the Diags screenTurn Load Off How to perform a total power offLoad off-Yes, turn Load off Total power off isolating one UPS in a parallel system How to perform a restart Restart single system with MBP Load on- Yes, turn Load on Configuration SettingsHow to change the Clock and the Alarms in the Setting menu  To go to Time Configuration Settings How to return parts to APC MaintenanceParts Replacement How to determine if you need a replacement partReplaceable parts only trained personnel How to store the battery modulesUser interface front How to replace and install a battery module How to replace a Network Management Card24 kg / 4 x 53 lbs   Xrups UPS / XR Troubleshooting Status and Alarm MessagesDisplay messages Troubleshooting Status and Alarm Messages See the section How to replace Display Message Meaning Corrective Action Page APC Worldwide Customer Support 990-2282A-00101/2007