APC 10-40 KVA 380/400/415 V manual Insert

Page 14

6. Insert the

XR Battery Enclosure rear view

UPS rear view

interconnection plates

 

 

 

between the two

 

 

enclosures. One is

 

 

 

 

 

positioned toward the

 

 

front and the other

 

toward the rear. Note

 

 

 

how the “wings” on

 

 

 

the interconnection

 

 

 

plates rest in slots at

 

 

 

the top of the inner

 

 

 

panel on the XR

 

 

 

Battery Enclosure.

 

 

 

7.

Align the two

 

enclosures and level

 

 

 

the three marked rows

 

 

of bolt holes in one

 

enclosure with the

 

holes in the adjacent

 

 

enclosure.

 

 

 

 

 

8.Push the two enclosures firmly together.

9.Bolt the two enclosures together by using the six M6x25 mm screws and nuts supplied in the kit: join one hole at

the front and one hole at the rear of the

 

 

 

 

 

 

 

 

 

 

enclosures on three levels.

UPS

 

 

 

 

 

 

XR

10.Position the last and third U-shaped

 

 

 

 

 

 

 

 

floor anchoring bracket under the

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

adjacent enclosure (see previous

 

 

 

 

 

 

 

 

 

 

graphics) and insert a minimum of two

 

 

 

 

 

 

 

 

 

 

floor anchoring M8 screws (not

 

 

 

 

 

 

 

 

 

 

provided) through holes in the bottom

 

 

 

 

 

 

 

 

 

 

of the enclosure and through holes in

 

 

the U-shaped floor anchoring bracket,

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

and into the predrilled floor holes, and

 

 

 

 

 

 

 

 

 

 

then fasten the screws.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

10

Smart-UPS VT ® 10-40 kVA 380/400/415 V, 208/220 V, 200/208 V Battery Installation

Image 14
Contents Installation Page Contents Post-Installation Checklist Safety Important Safety Instructions Save These InstructionsPrepare for Floor-Anchoring optional System arrangementsFour one in each corner. Recommended floor bolt size M8 Model width 352 mm 13.85 Remove the top cover Prepare for CablesRemove the front panel Remove the cable landing cover and bottom plates Remove the XR Battery Modules Shaped floor Page Insert Run the Cables Connect Power in Installations with BusbarsInstall isolators Install busbars UPS XR1 XR2 XR2 XR1 UPS See Connect the EPO on Connect Power in Installations with Cables Install power cablesFeed the cable up Connect Communication Cables Connect the EPO to the UPS and the XR Battery Enclosure Connect the EPOFinal Mechanical Assembly Level the enclosuresInstall battery-securing and floor-anchoring brackets Reinstall the Enclosure Plates Torque specification SpecificationsBattery voltage and current Recommended cable sizesPost-Installation Checklist Page Page Page 990-1740D-001 11/2009