Connect Power in Installations with Cables

Install power cables

See “Recommended cable sizes” on page 23.

Install power cables between the UPS and the XR Battery Enclosure.

1.In the UPS, feed the cable up through the conduit box or through the transparent cable route bracket (not shown).

2.Connect the Bat+, Bat-, and N cables to the busbars in the UPS.

3.Secure the cables to the perforated bracket with cable ties.

4.Equip the cable with conduits (if applicable).

5.In the XR Battery Enclosure, feed the cable up through the conduit box (if applicable) to the cable landing area.

6.Connect the (+) cable to busbar no. 1 (+), connect the N cable to busbar no. 4 (N), and the (-) cable to busbar no. 6 (-).

7.Secure the cable to the perforated bracket with cable ties.

8.Attach the top part of the conduit box (if applicable).

XR Battery Enclosure rear view

BAT

BAT

XR2

To

 

UPS rear view.

BAT

BAT

16

Smart-UPS VT ® 10-40 kVA 380/400/415 V, 208/220 V, 200/208 V Battery Installation

Image 20
Contents Installation Page Contents Post-Installation Checklist Safety Important Safety Instructions Save These InstructionsPrepare for Floor-Anchoring optional System arrangementsFour one in each corner. Recommended floor bolt size M8 Model width 352 mm 13.85 Remove the top cover Prepare for CablesRemove the front panel Remove the cable landing cover and bottom plates Remove the XR Battery Modules Shaped floor Page Insert Run the Cables Connect Power in Installations with BusbarsInstall isolators Install busbars UPS XR1 XR2 XR2 XR1 UPS See Connect the EPO on Connect Power in Installations with Cables Install power cablesFeed the cable up Connect Communication Cables Connect the EPO to the UPS and the XR Battery Enclosure Connect the EPOFinal Mechanical Assembly Level the enclosuresInstall battery-securing and floor-anchoring brackets Reinstall the Enclosure Plates Specifications Battery voltage and currentTorque specification Recommended cable sizesPost-Installation Checklist Page Page Page 990-1740D-001 11/2009