Connect Communication Cables

XR

UPS

 

 

 

BAT

 

 

 

 

BAT

 

 

 

1.Feed the cable from pin connection J106 in the UPS down through the conduit (if appliccable).

2.Run the cable up into the XR conduit and connect it to pin connection J200 in the XR Battery Enclosure.

3.If you use an XR2, run the cable from pin connection J204 in XR1 to pin connection J200 in XR2.

18

Smart-UPS VT ® 10-40 kVA 380/400/415 V, 208/220 V, 200/208 V Battery Installation

Image 22
Contents Installation Page Contents Post-Installation Checklist Safety Important Safety Instructions Save These InstructionsPrepare for Floor-Anchoring optional System arrangementsFour one in each corner. Recommended floor bolt size M8 Model width 352 mm 13.85 Remove the front panel Prepare for CablesRemove the top cover Remove the cable landing cover and bottom plates Remove the XR Battery Modules Shaped floor Page Insert Install isolators Connect Power in Installations with BusbarsRun the Cables Install busbars UPS XR1 XR2 XR2 XR1 UPS See Connect the EPO on Connect Power in Installations with Cables Install power cablesFeed the cable up Connect Communication Cables Connect the EPO to the UPS and the XR Battery Enclosure Connect the EPOFinal Mechanical Assembly Level the enclosuresInstall battery-securing and floor-anchoring brackets Reinstall the Enclosure Plates Torque specification SpecificationsBattery voltage and current Recommended cable sizesPost-Installation Checklist Page Page Page 990-1740D-001 11/2009