523 mm (20.59 in) UPS system with the UPS placed to the right (seen from the front).

UPS

XR1

XR2

N

+

1.Install the following baying kit busbars between the UPS and XR1:

880-1607 between the vertical busbar N on the UPS and busbar 3 on XR1 880-1605 between vertical busbar (+) on the UPS and busbar 1 on XR1 880-1606 between vertical busbar (-) on the UPS and busbar 6 on XR1

2.Install the following baying kit busbars between the two XR Battery Enclosures: 880-0926 between the vertical busbar 4 on XR1 and vertical busbar 3 on XR2 880-0941 between the vertical busbar 2 on XR 1 and vertical busbar 2 on XR2 880-0940 between the vertical busbar 5 on XR1 and vertical busbar 5 on XR2

Smart-UPS VT ® 10-40 kVA 380/400/415 V, 208/220 V, 200/208 V Battery Installation

13

Image 17
Contents Installation Page Contents Post-Installation Checklist Important Safety Instructions Save These Instructions SafetySystem arrangements Prepare for Floor-Anchoring optionalFour one in each corner. Recommended floor bolt size M8 Model width 352 mm 13.85 Remove the top cover Prepare for CablesRemove the front panel Remove the cable landing cover and bottom plates Remove the XR Battery Modules Shaped floor Page Insert Run the Cables Connect Power in Installations with BusbarsInstall isolators Install busbars UPS XR1 XR2 XR2 XR1 UPS See Connect the EPO on Install power cables Connect Power in Installations with CablesFeed the cable up Connect Communication Cables Connect the EPO Connect the EPO to the UPS and the XR Battery EnclosureLevel the enclosures Final Mechanical AssemblyInstall battery-securing and floor-anchoring brackets Reinstall the Enclosure Plates Battery voltage and current SpecificationsTorque specification Recommended cable sizesPost-Installation Checklist Page Page Page 11/2009 990-1740D-001