APC 10-40 KVA 380/400/415 V Specifications, Battery voltage and current, Recommended cable sizes

Page 27

Specifications

Battery voltage and current

XR Battery Enclosure

30 kVA

40 kVA

 

 

 

Battery voltage (nominal)

± 192 VDC

± 192 VDC

 

 

 

Battery current (at full load)

69.4 A at ± 192 V

87.9A at ± 192V

 

 

 

Max. current (at end of discharge)

86.6 A at ± 154 V

110.1A at ± 154V

 

 

 

If the XR Battery Enclosure is customer-supplied, please refer

 

 

to product-specific data.

 

 

 

 

 

Recommended cable sizes

North America

Europe, Middle East, Asia

Japan

 

 

 

208/220 V

380/400/415 V

200/208 V

 

 

 

BAT+, N, BAT- 1 AWG 167º F

BAT+, N, BAT- 50 mm2 75º C

BAT+, N, BAT- 50 mm2 75º C copper

(75º C) copper wire

(167º F) copper wire

wire.

 

 

Use only 8,08-1,3 mm2 copper wire rated

 

 

minimum 250 V.

 

 

 

Note: Power terminal lug diameter: minimum 6 mm (0.2 in).

Torque value: 45 lbf-in/7 Nm.

Note: Use Molex lug type or equivalent, and follow the manufacturer’s specifications.

EPO requirements

SELV voltage

Current:

24 VDC

1500 mA

Torque specification

Torque specification: Isolators: M5 7 Nm (45 lbf-in).

Smart-UPS VT ® 10-40 kVA 380/400/415 V, 208/220 V, 200/208 V Battery Installation

23

Image 27
Contents Installation Page Contents Post-Installation Checklist Important Safety Instructions Save These Instructions SafetySystem arrangements Prepare for Floor-Anchoring optionalFour one in each corner. Recommended floor bolt size M8 Model width 352 mm 13.85 Prepare for Cables Remove the front panelRemove the top cover Remove the cable landing cover and bottom plates Remove the XR Battery Modules Shaped floor Page Insert Connect Power in Installations with Busbars Install isolatorsRun the Cables Install busbars UPS XR1 XR2 XR2 XR1 UPS See Connect the EPO on Install power cables Connect Power in Installations with CablesFeed the cable up Connect Communication Cables Connect the EPO Connect the EPO to the UPS and the XR Battery EnclosureLevel the enclosures Final Mechanical AssemblyInstall battery-securing and floor-anchoring brackets Reinstall the Enclosure Plates Recommended cable sizes SpecificationsBattery voltage and current Torque specificationPost-Installation Checklist Page Page Page 11/2009 990-1740D-001