APC 10-40 KVA 380/400/415 V manual Install battery-securing and floor-anchoring brackets

Page 25

Install battery-securing and floor-anchoring brackets

Battery securing bracket

L-shaped floor-anchoring bracket (reuse of transportation bracket)

1.Install the batteries by pushing them all the way into the enclosure.

2.If required, install the battery securing brackets to hold the batteries firmly in place. Note! Do not install the bracket the same way they were positioned when the enclosure arrived. Rotate the brackets 180º and reinstall.

Note: Battery securing brackets are delivered with the UPS or XR Battery Enclosure and installed in front of the batteries. Extra battery securing brackets for additional batteries can be purchased. Refer to kit SUVTOPT003: APC Smart-UPS VT Battery Lock Kit for one Battery Module.

3.Install the L-shaped floor-anchoring bracket (reuse of transportation brackets) by adding four M6 screws and nuts (provided) to the enclosure (only if the optional U-shaped floor anchoring brackets described in this manual have not been chosen).

4.Drill floor holes.

Note: If the floor has not been prepared for anchoring, see “Prepare for Floor-Anchoring (optional)” on page 2.

5.Add a minimum of two M8 screws (not provided) to the anchoring bracket and tighten the screws.

Smart-UPS VT ® 10-40 kVA 380/400/415 V, 208/220 V, 200/208 V Battery Installation

21

Image 25
Contents Installation Page Contents Post-Installation Checklist Important Safety Instructions Save These Instructions SafetySystem arrangements Prepare for Floor-Anchoring optionalFour one in each corner. Recommended floor bolt size M8 Model width 352 mm 13.85 Remove the front panel Prepare for CablesRemove the top cover Remove the cable landing cover and bottom plates Remove the XR Battery Modules Shaped floor Page Insert Install isolators Connect Power in Installations with BusbarsRun the Cables Install busbars UPS XR1 XR2 XR2 XR1 UPS See Connect the EPO on Install power cables Connect Power in Installations with CablesFeed the cable up Connect Communication Cables Connect the EPO Connect the EPO to the UPS and the XR Battery EnclosureLevel the enclosures Final Mechanical AssemblyInstall battery-securing and floor-anchoring brackets Reinstall the Enclosure Plates Battery voltage and current SpecificationsTorque specification Recommended cable sizesPost-Installation Checklist Page Page Page 11/2009 990-1740D-001