APC 10-40 KVA 380/400/415 V manual

Page 31
Image 31
Contents Installation Page Contents Post-Installation Checklist Important Safety Instructions Save These Instructions SafetySystem arrangements Prepare for Floor-Anchoring optionalFour one in each corner. Recommended floor bolt size M8 Model width 352 mm 13.85 Remove the front panel Prepare for CablesRemove the top cover Remove the cable landing cover and bottom plates Remove the XR Battery Modules Shaped floor Page Insert Install isolators Connect Power in Installations with BusbarsRun the Cables Install busbars UPS XR1 XR2 XR2 XR1 UPS See Connect the EPO on Install power cables Connect Power in Installations with CablesFeed the cable up Connect Communication Cables Connect the EPO Connect the EPO to the UPS and the XR Battery EnclosureLevel the enclosures Final Mechanical AssemblyInstall battery-securing and floor-anchoring brackets Reinstall the Enclosure Plates Recommended cable sizes SpecificationsBattery voltage and current Torque specificationPost-Installation Checklist Page Page Page 11/2009 990-1740D-001