APC 10-40 KVA 380/400/415 V manual Run the Cables, Connect Power in Installations with Busbars

Page 15

Run the Cables

Connect Power in Installations with Busbars

Warning: Before carrying out the steps below, you must follow the Total Power Off procedure in the Operation manual.

Install isolators

See “Specifications” on page 23 for torque specification.

The isolators separate the baying kit busbar from the six vertical busbars in each XR Battery Enclosure, and the (+), N, and (-) busbars in the UPS. This is how the isolators are fitted to their busbar:

1.Guide the isolator busbar through the adjacent side panels.

+

N

2.Position the isolators across the vertical busbars (N in this example) and then fasten the isolator busbar by using the provided M5 Torx screws.

3.Secure the isolator to its busbar with cable ties.

+

N

 

N

 

Smart-UPS VT ® 10-40 kVA 380/400/415 V, 208/220 V, 200/208 V Battery Installation

11

Image 15
Contents Installation Page Contents Post-Installation Checklist Important Safety Instructions Save These Instructions SafetySystem arrangements Prepare for Floor-Anchoring optionalFour one in each corner. Recommended floor bolt size M8 Model width 352 mm 13.85 Prepare for Cables Remove the front panelRemove the top cover Remove the cable landing cover and bottom plates Remove the XR Battery Modules Shaped floor Page Insert Connect Power in Installations with Busbars Install isolatorsRun the Cables Install busbars UPS XR1 XR2 XR2 XR1 UPS See Connect the EPO on Install power cables Connect Power in Installations with CablesFeed the cable up Connect Communication Cables Connect the EPO Connect the EPO to the UPS and the XR Battery EnclosureLevel the enclosures Final Mechanical AssemblyInstall battery-securing and floor-anchoring brackets Reinstall the Enclosure Plates Recommended cable sizes SpecificationsBattery voltage and current Torque specificationPost-Installation Checklist Page Page Page 11/2009 990-1740D-001