DataNET Copper Connections, Continued
Down Link Wiring with DataNET Hub Signal Equalizer Board
Step | Action |
1.Plug the DataNET Hub Signal Equalizer Board into the se- lected Port interface connector.
2.Connect the board’s pig tail leads to the corresponding hub downlink port channel; red lead to (+) terminal, black lead to
Master Port
Connectors
TB15 – TB18
3.Connect the downlink signal wires to the removable port connector (TB1) on top of the equalizer board. Positive to
(+) terminal; and Negative to
|
|
|
| GND | - + |
|
| |
|
|
|
|
|
|
|
| |
TB1Port |
|
|
|
|
|
| ||
|
|
|
|
|
| |||
Connector |
|
|
|
|
|
|
| |
|
|
|
|
|
| SW2 | ||
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| SW3 |
|
|
|
|
|
| |
|
|
|
|
| SW1 | |||
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
Board
Connector
.
4.If conduit is used the cable shield is only terminated at one end of the cable. If shield is terminated at this end connect it to terminal 3 (GND) on board. If using cable gland connec- tors, cable gland will always connect the shield to the chas- sis.
5.Set the switches on the board to the correct settings; see DataNET Hub Signal Equalizer Board Settings page 34.
32 • Installation |