Extron electronic MKP 2000 user manual Three, Local Operation, Power supply wiring

Page 14

Installation, cont’d

Power supply wiring

Figure 2-12 shows how to wire the connector.

Smooth

Ridges

 

0.2” (5 mm)

 

A

 

A

 

 

 

 

 

 

 

 

 

 

 

 

 

 

SECTION A–A

 

 

 

 

 

 

 

 

 

 

12V GND

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Power Supply

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Output Cord

 

 

 

 

Direct Insertion

 

 

 

 

 

 

 

 

Connector

Figure 2-12 — Power connector wiring

 

 

 

Power supply voltage polarity is critical. Incorrect

 

CAUTION

 

 

 

 

voltage polarity can damage the power supply and

the MKP. Identify the power cord negative lead by the ridges on the side of the cord (figure 2-12).

To verify the polarity before connection, plug in the power supply with no load and check the output with a voltmeter.

CAUTION

The length of the exposed (stripped) copper wires is

 

important. The ideal length is 0.2" (5 mm).

 

Longer bare wires can short together. Shorter wires

 

are not as secure in the direct insertion connectors

 

and could be pulled out.

Do not tin the power supply leads before installing in the direct insertion connector. Tinned wires are not as secure in the connectors and could be pulled out.

The two power cord wires must be kept separate while the power supply is plugged in. Remove power before wiring.

Alternatively, an Extron P/S 100 Universal 12 VDC Power Supply, part #60-357-01, can power up to ten Extron 12 VDC devices using only one AC power connector.

MKP 2000 Remote Control Panel

Chapter3Three

Local Operation

Front Panel Controls and Indications

Front Panel Operations

Rear Panel Resets

2-14 MKP 2000 Remote Control Panel • Installation

Image 14
Contents Remote Control Panel MKPPrecautions Extron’s WarrantyQuick Start Guide MKP Table of Contents One MKP 2000 Remote Control PanelTable of Contents, cont’d IntroductionEthernet connection to the switcher About the MKP 2000 Remote Control PanelRS-232 connection to the switcher MKP 2000 Remote Control Panel IntroductionInstallation TwoUL Requirements for Wall Box Installation InstallationMKP Installation Overview Installation ProceduresInstalled in a wall box Installation, cont’dPreparing the site, installing the mud ring or wall box To meet the UL listing requirements, this device must beMounting the MKP to the mud ring or wall box Detail aSwitch Rear Panel and Side Panel ConnectionsControl connections RS-232 cable termination11 RJ-45 connector and pinout tables TP cable terminationLocal Operation Power supply wiringThree Front Panel Controls and Indications MKP 2000 Remote Control Panel Local OperationLocal Operation Front Panel OperationsViewing the last input or output tied from the MKP Viewing and configuring the IP and MKP set-up parametersLocal Operation, cont’d Host control port setting and pass-through communications Input Output TakePerforming soft resets Rear Panel ResetsControl panel security lockout executive mode SIS Operation Performing a hard resetFour Ethernet Link SIS OperationRS-232 Links Host-to-MKP InstructionsSIS Operation, cont’d MKP Error ResponsesUsing the Command/Response Table Where Symbol definitions for MKP SIS commandsXxx.xx Command/response table for MKP SIS commands MKP SIS OperationCont’d Five Html OperationDownload the Startup MKP 2000 Remote Control Panel Html OperationHtml Operation System Settings Html Operation, cont’d System StatusHtml Operation, cont’d IP Settings sectionSwitcher Settings section Front panel configuration lock Port RS-232 SettingsDate/Time Settings fields Authorized inputs and authorized outputsHtml Operation, cont’d Passwords Firmware UpgradeFile Management Html Operation, cont’d Special Characters AAppendix aReference Data Part Numbers SpecificationsReference Data Panel mount cutout template Reference Data, cont’d Mounting and Cabling SpecificationsElectrical box cutout Drawn to scale may be used as a templateReference Data, cont’d Extron Comm-Link cable