6. Dryer Start-Up

Adjusting the Temperature

1.Press the PROGRAM(TEMPERATURES) button until the “carrot” is above the timer to be modified.

2.Use the UP and DOWN arrow keys to change the present temperature to the desired setting. The new temperature is automatically accepted.

3.Keep pressing the PROGRAM(TEMPERATURES) button until the carrot disappears or press the MODE SELECT button once to exit.

4.On LP gas models, adjust the PRESSURE REGULATOR (high-fire) on the burner fuel line, so that burner will reach the thermostat setting and switch to low-fire. Pressure up to 25 lbs. may be required. Natural gas does not have a regulator, but uses a LARGE BALL VALVE close to the vertical supply line for adjustment. Pressure up to 18 lbs. may be required.

The Approximate Settings should be:

LP Gas

Natural Gas

 

 

 

 

High-Fire 6-15 lbs.

High-Fire 6-10 lbs.

 

 

Low-Fire 2-6 lbs.

Low-Fire 1-3 lbs.

 

 

Do not set the low-fire pressure so low that a popping or fluttering sound is heard in the heater. If popping or fluttering sound are heard, increase the pressure until the sound goes away.

On LP and NG gas models adjust the needle valve on the cycle solenoid (low-fire valve) so that the burner maintains flame then switches back to high-fire.

5.Adjust the burner pressure so that the burner CYCLES 2 to 3 times per minute (approximately 15 to 20 seconds on HIGH and approximately 5-8 seconds on LOW). Increasing the gas pressure with the LP gas regulator or the Natural Gas hand valve increases the cycling rate and lowering it decreases the rate. This is the primary way to change the cycling rate.

Decreasing the low pressure setting with the needle valve will also increase the rate while increasing that pressure will decrease the rate.

6.On LP gas models adjust the vaporizer so the fuel pipes going to the burner from the regulator are warm to the touch (not hot and cold).

The vaporizer can be adjusted two ways. First, by loosening the bolt in the hinging mechanism and swinging it to a hotter or cooler position. Second, by loosening the two bolts in the hinge pipe and sliding the vaporizer in or out to a cooler or hotter position. Either one or both methods may need to be used to get the vaporizer to the proper temperature, but the first almost always gives adequate adjustment. Natural gas does not use a vaporizer.

PNEG-552100 Series Dryer

31

Image 31
Contents Series Dryer PNEG-552100 Series Dryer Contents Table of Contents Safety Guidelines Emergency Stop Dryer OperationUse Caution in the Operation of this Equipment Safety PrecautionsDecal DC-889 Decal DC-1224Decal DC-972 Safety Alert DecalsDecal DC-1225 Decal DC-1227Decal DC-1229 Decal DC-973 RegulationsDryer Control Panel Moisture Control Dryer Control Panel Featuring the 100 Series Control SystemUnload Switch Dryer Power Stop Switch Setting the Dry, Cool, Unload and Out of Grain Timers Monitoring Grain Temperatures, Plenum Temperature or Timers Safety Circuit Shut Down Messages Special FeaturesLoss of Flame Error Conditions Error Conditions Inspect the Metering Rolls Set Control SwitchesFuel Check Electrical PowerControl Power Switch Power Start ButtonMetering Roll Operation Fan SwitchLP Gas Natural Gas Burner SafetyHeater Test Fire Staged Batch CheckStopping Dryer Operation Dryer Shut DownRef # Description Full Start-Up Check Continuous Flow OperationFilling the Dryer Staged Batch Operation Fan Setting Heater Setting Fan Function Heater FunctionPNEG-552 100 Series Dryer Starting the Dryer Series Batch Timer SettingsAdjusting the Temperature Full Heat Continuous Flow Operation Initial Moisture Full Heat Approximate Adjusting the Moisture ControlMoisture % Removed pts Speed Dry Time min Low High Hours of Service per Year Range Suggested Lube Interval Seasonal Inspection and ServiceInsulation Class Consistency Type Grease Frame Type Lubrication ProceduresSuggested Lubricants Additional ChecksRef # Description Threaded Bushing Holes Fan Propeller Removal and InstallationClearance Holes Fan Blade Removal Fan Motor Removal and InstallationPosition of Fan Motor Heater Parts Removal and Installation Main Controls Metering Roll ServicingAs necessary. See F How to Determine a Metering Roll ProblemHow to Clear a Jammed Metering Roll Series Single Fan Wiring to Control Box Series Front Panel External Wiring Series Front Panel Internal Wiring Series Lower Back Panel Wiring Series External Wiring to Dryer Series Upper Control Box Wiring Series Main Power Wiring Series Control Schematic Series Control Schematic PNEG-552 100 Series Dryer Series 220 Volt 1 Phase Power Schematic Series 220VAC 3 Phase Power Schematic Series 440VAC 3 Phase Power Schematic Press the dryer power start button Problem Possible CauseDisplay shows Vapor High Temperature Display shows Rear Discharge Warning Display shows Plenum High TemperatureDisplay shows Grain High Temperature Plenum High Temperature messages atTroubleshooting Wires connected together, the thermostat is faulty FAQs PNEG-552100 Series Dryer GSI Group Warranty