Carrier 17EX External Gear Pre-Start Checks, Recommended Motor Fastener Tightening Torques

Page 51

2.Direct current (as from a welder) can be passed through the winding. The total current should not exceed approxi- mately 50% of the rated full load current. If the motor has only 3 leads, 2 must be connected together to form one circuit through the winding. In this case, one phase carries the full applied current and each of the others car- ries half of the applied current. If the motor has 6 leads (3 mains and 3 neutrals), the 3 phases should be con- nected into one series circuit.

3.Heated air can be blown either directly into the motor or into a temporary enclosure surrounding the motor. The source of heated air should preferably be electrical vs. fueled (such as kerosene), since a malfunction of the fuel burner could result in carbon entering the motor. Exer- cise caution when heating the motor with any source of heat other than self-contained space heaters. Raise the wind- ing temperature at a gradual rate to allow any entrapped moisture to vaporize and escape without rupturing the in- sulation. The entire heating cycle should extend over 15 to 20 hours.

Insulation resistance measurements can be made while the winding is being heated. However, they must be corrected to 104 F (40 C) for evaluation since the actual insulation re- sistance decreases with increasing temperature. For a new winding, the insulation resistance approximately halves for each 18° F (10° C) increase in insulation temperature above the dew point.

Motor Pre-Start Checks Ð To prevent damage to the motor, the following steps must be taken before initial start- up:

1.Remove the shaft shipping brace (if supplied).

2.For sleeve bearing motors, the oil reservoir must be ®lled with oil to the correct level. Use a rust and oxidation in- hibited, turbine grade oil. The viscosity of the oil must be 32 ISO (150 SSU) at 100 F (37.7 C). Oil capacity in each of the two bearings is 0.6 gal. (2.3 L) per bearing. Use of Carrier Oil Speci®cation PP16-0 is approved, Carrier Part No. PP23BZ091 (Mobil DTE Light or Texaco Regal R+O32).

3.If possible, the shaft should be turned over by hand to ensure that there is free rotation. On sleeve bearing mo- tors, the shaft should be moved to both extremes of its end play while it is being rotated, and the oil rings should be viewed through the viewing ports in the top of the bear- ing housing to verify free ring rotation.

4.On fan-cooled motors, the area around the external fan inlet should be checked for loose debris that could be drawn into the fan during operation.

5.All external, factory-made, bolted joints should be checked for any looseness that may have occurred in transit. Refer to Table 6 for recommended bolt torques.

Table 6 Ð Recommended Motor Fastener

Tightening Torques

 

 

Bolt size

 

1¤4

5¤16

 

3¤8

 

1¤2

 

5¤8

3¤4

 

7¤8

 

1

 

11¤3

 

11¤2

 

 

Grade

 

 

 

 

 

 

 

 

 

 

 

SAE GR 5

 

 

 

 

 

 

Torque*

 

Ft-lbs

 

3.5

7

 

12

 

31

 

63

115

 

180

275

550

 

960

 

N.m

 

4.7

9.5

16

 

42

 

85

156

244

373

746

1302

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Bolt size

 

M4

 

M6

 

M8

 

M10

 

M12

 

M10

 

M12

 

M16

 

 

Grade

 

 

 

 

 

 

DIN 8.8

 

 

 

 

 

 

DIN 12.9

 

Torque*

Ft-lbs

 

2

 

 

8

 

15

 

35

 

65

 

 

45

 

92

 

225

N.m

 

2.7

 

11

 

20

 

47

 

88

 

 

61

 

125

 

305

 

 

 

 

 

 

 

 

 

 

 

*Torque values based upon dry friction.

External Gear Pre-Start Checks

There are 2 service valves on the external gear oil lines. See Fig. 27. Open both valves before starting the chiller.

External gears are shipped without oil. Before start-up, the gear must be ®lled with the proper type and amount of oil.

Before starting the external gear, check for any signs of mechanical damage, such as damaged piping or accessories. Then, follow the procedures listed below.

1.Fill the gear and auxiliary sump (if applicable) with oil to the level indicated next to the sight glass. Fill the gear to the proper level as follows. Make sure all external pip- ing, gear oil cooler, and pumps are ®lled before con®rm- ing the ®nal oil level. Fill to the oil level indicated next to the glass sight gage.

Add oil through the gear inspection cover. The inspection cover must be removed in order to add oil. Take care to seal the cover when it is replaced.

Never attempt to add or replace oil while the ex- ternal gear is running unless a vertical sight glass is in use and the running oil level has been established and marked on the sight glass. Do not ®ll beyond the indicated oil level. Excess lubrication increases the churning effect and may result in overheating and subsequent thinning of oil and possible damage to the rotating components.

2.The viscosity of the oil must be 68 ISO. Use of Carrier oil, speci®cation PP16-2 is approved (Mobil DTE Heavy Medium or Texaco Regal UR & 068; Carrier Part No. PP23BB005).

3.Check that all electrical connections have been made and are in working order. Check that all accessories are prop- erly mounted.

4.Turn the gear shafts by hand with a spanner wrench to con®rm that there are no obstructions to rotation.

5.Check that all couplings are properly aligned, mounted, and keyed on the shaft extension.

6.Check that the inspection cover is securely fastened. See Table 7 for recommended torque values.

7.For units operating in cold ambient temperatures, op- tional heaters must be turned on and the oil temperature must be allowed to rise to at least 60 F (16 C) before start-up.

8.Start the chiller under as light a load as possible. Check for oil leaks, unusual sounds, excessive vibration, and ex- cessive heat. If an operating problem develops, shut down immediately and correct the problem before restarting.

51

Image 51
Contents Safety Considerations Start-Up, Operation, and Maintenance InstructionsContents Inspect Water Piping Piping Check Relief Devices Inspect WiringOCCPC01S Input Service Congurations Coupling Maintenance Motor MaintenanceContents Introduction Abbreviations17EX Chiller Familiarization Certified PerformanceTypical 17EX Chiller Components Lubrication Cycle OIL Cooling CycleRefrigeration, Cycle Starters17EX Compressor Lubrication Cycle Denitions ControlsProcessor Sensor Input/Output Module Control Center Temperature Sensors See Fig Pressure TransducersMajor PIC Components Panel Locations PIC Component Panel Location17EX Controls and Sensor Locations LID PICPsio Equip GND Ð GRDTewac LID Operation and Menus Fig PROCESSOR/SENSOR INPUT/OUTPUT Module PsioGeneral LID Service Screen Override Operations YES or no , on or OFF , etc. to select the desired state17EX LID Menu Structure Default ScreenControl Test Service TableAlarm History Equipment ConfigurationLID CCNCarrier Comfort Network Hgbp Ð Hot Gas BypassHgbp SetpointChwr ChwsMenu Status Select Description Range Units Reference Point Name Alarm HistoryLID Display Data Example 1 Ð STATUS01 Display ScreenExample 2 Ð STATUS02 Display Screen Example 3 Ð STATUS03 Display ScreenMenu Status Example 4 Ð STATUS04 Display Screen Example 5 Ð Setpoint Display ScreenMenu Example 6 Ð Configuration Config Display Screen ECW Control OptionICE Build Termination LAG =2, Standby =3 Example 7 Ð LEAD/LAG Configuration Display ScreenExample 8 Ð SERVICE1 Display Screen Menu Service Example 9 Ð SERVICE2 Display ScreenSpare Alert Enable Example 10 Ð SERVICE3 Display ScreenBearing Temperature Example 11 Ð Maintenance MAINT01 Display ScreenExample 12 Ð Maintenance MAINT02 Display Screen Discharge TemperatureExample 13 Ð Maintenance MAINT03 Display Screen Example 14 Ð Maintenance MAINT04 Display ScreenDescription RANGE/STATUS Units Reference Point Name PIC System Functions Page Protective Safety Limits and Control Settings Capacity Overrides Page Page ECW Cent Capacity ICE Build Setpoint Example of Attach to Network Device Screen Example of Holiday Period Screen To Access the Service ScreensRecycle Sequence Fig START-UP/SHUTDOWNPage Motor Before Initial START-UPJob Data Required Equipment RequiredPage 17EX Leak Test Procedures Temperature C Ð HFC-134a Pressure Ð Temperature FÐ HFC-134a Pressure Ð Temperature C Temperature FDehydration Cold Trap Inspect Wiring Check Optional Pumpout Compressor Water Pip900 500 901 7000 1000 7001-14500 2500 Recommended Motor Fastener Tightening Torques External Gear Pre-Start ChecksExternal Gear Lubrication System Check Starter Mechanical StartersSOLID-STATE Starters Set Up Chiller Control Conguration Input the Design Set Points Ð To modify the setInput the Local Occupied Schedule OCCPC01S Change the LID Configuration if Necessary Surge Limiting orT1/P1 Full Load Points T2/P2 Load Surge Prevention Occurs TOO Soon Occurs TOO Late Increase P1 by Decrease P1 by50% Tests to be Devices Tested Performed Charge Refrigerant into ChillerInitial START-UP Control Test Menu FunctionsDry Run to Test Start-Up Sequence Check Motor RotationInitial Motor START-UP Page Flange Nut Tightening Torques Low Speed Couplings Only General Recommendations Calibrate Motor Current Demand SettingCheck Oil Pressure and Compressor Stop To Prevent Accidental Start-Up Ð The PIC can beStopping the Chiller Operating InstructionsOperator Duties Starting the ChillerOperating the Optional Pumpout Compressor Pumpout and Refrigerant Transfer ProceduresPlant Chiller Serial No Chiller Model No Refrigerant Type Rear View Valve Condition RLAReturn Chiller to Normal Operating Conditions General MaintenanceChecking Guide Vane Linkage Ð Refer to Fig Contact Seal Maintenance Refer to ÐContact Seal Page Checking Preliminary Alignment Chiller AlignmentMeasuring Angular Misalignment Elevation Alignment Formula HOT Alignment Check Adjusting Angular Misalignment in PlanDoweling Correcting Parallel MisalignmentChanging the Oil Filters Weekly MaintenanceScheduled Maintenance Check Safety and Operating Controls MonthlyCompressor OIL 17EX Chiller Oil SpecicationsPumpout Typical Float Valve Arrangement Sleeve Bearings Page Motor Riggings Inspect the Heat Exchanger Tubes Controls for Optional Pumpout Compressor Troubleshooting GuidePage MAINT04 MAINT01MAINT02 MAINT03PIC 1CR AUXOilpd OiltAutorestart in Progress Starts Limit ExceededFailure to Stop FaultOperation Potential FREEZE-UPRunning Ð Demand Limited Running Ð Temp ControlChiller Protect Limit Faults Autorestart Pending Sensor Fault AlertLOW OIL Pressure AlertDESCRIPTION/MALFUNCTION Probable CAUSE/REMEDY Possible Cause Action External Gear Troubleshooting GuideProblem Possible Cause Ð Item NO.sTemperature Voltage Resistance Drop Ð Thermistor Temperature F vs Resistance/Voltage DropTemperature Voltage Resistance Drop Ð Thermistor Temperature C vs Resistance/Voltage DropInput Options Module Module SwitchControl Modules Module AddressProcessor/Sensor Input/Output Module Psio Fig Starter Management Module SMM FigGRD Options Module Installation of NEW Psio ModuleSwitch Setting Options Module Four-In/Two-Out Module Fig4-In/2-Out Module Physical Data and Wiring Schematics100 Additional Cooler WeightsWeight Vessel SIZE² Condenser Total Weight Condenser Charge101 Additional Condenser WeightsCompressor Weight and Elbow Weight Drive Component WeightsÐ Total Motor Weight, English lb Ð Total Motor Weight, SI kg102 103 Marine Waterbox Cover WeightsNIH Waterbox Cover Weights Approximate Refrigerant HCFC-134a ChargeAuxiliary Systems, Electrical Data Relief Valve Locations and Data104 105 Compressor Fits and Clearances106 Clearance Type DescriptionMeasure Tabulation Ð Impeller Clearances Open-Drive Compressors 10717FX 108 Tewac 109Temp Press110 111 112 General 113Terminal Strip 114GND Ð Ground T1-T4Index Index Index Index Index Copyright 1997 Carrier Corporation

17EX specifications

The Carrier 17EX is recognized as an innovative air conditioning solution that combines efficiency with advanced technology. This model is designed to meet the increasing demands of residential and commercial cooling needs while maintaining environmental consciousness.

One of the standout features of the Carrier 17EX is its impressive Seasonal Energy Efficiency Ratio (SEER) rating. With a SEER rating that often exceeds 17, this unit ensures optimized energy consumption, significantly lowering operational costs for users. The incorporation of advanced compressor technology allows the system to adjust its cooling output based on the specific needs of the environment, thus providing both comfort and energy savings.

The Carrier 17EX utilizes a variable-speed inverter-driven compressor that enhances its performance and adaptability. This technology allows the air conditioning unit to operate at different speeds, intelligently adjusting to changing load conditions. As a result, the system runs more efficiently and quietly, providing a more consistent comfort level without the abrupt temperature swings associated with traditional units.

In addition to efficiency, the Carrier 17EX also prioritizes reliability and durability. The unit comes with a robust cabinet that protects the components from weather elements, ensuring longevity and consistent performance. The innovative design integrates a corrosion-resistant finish and robust insulation, which further enhances the unit's resilience in various environmental conditions.

For users concerned about indoor air quality, the Carrier 17EX includes advanced filtration systems designed to capture allergens and airborne particles. This feature is particularly beneficial for individuals with respiratory issues, ensuring that the air circulated within the space is clean and healthy.

Moreover, the Carrier 17EX is equipped with smart technology capabilities, allowing users to control their systems remotely through smartphones or other smart devices. This connectivity not only provides convenience but also empowers homeowners to optimize their energy use by adjusting settings on the fly, ensuring efficient operation even when they are away from home.

Overall, the Carrier 17EX stands out in the marketplace for its exceptional energy efficiency, advanced technology, and commitment to providing reliable and effective cooling solutions. Its combination of modern features makes it a preferred choice for those looking to enhance comfort while being mindful of energy consumption and environmental impact.