Carrier 17EX specifications

Page 46

The rotation direction of the motor is shown either on the motor nameplate or on the certi®ed drawing. Information on the required phase rotation of the incoming power for this motor may also be found on the nameplate or drawing. If either is unknown, the correct sequence can be determined as follows. While the motor is uncoupled from the load, start the motor and observe the direction of rotation. Allow the motor to achieve full speed before disconnecting it from the power source. Refer to Motor Pre-Start Checks (page 51) for information concerning initial start-up. If the resulting rotation is incorrect, it can be reversed by interchanging any 2 incoming cables.

Motor Auxiliary Devices Ð Auxiliary devices such as resistance temperature detectors, thermocouples, thermo- guards, etc., generally terminate on terminal blocks located in the auxiliary terminal box on the motor. Other devices may terminate on their own enclosures elsewhere on the mo- tor. Such information can be obtained by referring to the cer- ti®ed drawing. Information regarding terminal designations and the connection of auxiliary devices can be obtained from the auxiliary drawings referenced by the outline drawing.

If the motor is provided with internal space heaters, to ensure proper heater operation, the incoming voltage sup- plied to them must be exactly as shown by either the name- plate on the motor or the outline drawing. Exercise caution any time contact is made with the incoming space heater cir- cuit, because space heater voltage is often automatically ap- plied when the motor is shut down.

Open Oil Circuit Valves Ð Check that the oil ®lter isolation valves for both the compressor and external gear are open by removing the valve cap and checking the valve stem. (See Scheduled Maintenance, Changing the Oil Fil- ters, page 76.)

Tighten All Gasketed Joints and Guide Vane Shaft Packing Ð Gaskets and packings normally relax by the time the chiller arrives at the jobsite. Tighten all gas- keted joints and the guide vane shaft packing to ensure a leak-tight chiller.

NOTE: Check the chiller cold alignment. Refer to Chiller Alignment in the General Maintenance section, page 71.

Check Chiller Tightness Ð Figure 25 outlines the proper sequence and procedures for leak testing.

17EX chillers may be shipped with the refrigerant con- tained in the economizer/storage vessel and the oil charge shipped in the compressor. The cooler/condenser vessels have a 15 psig (103 kPa) refrigerant charge. Units may also be ordered with the refrigerant shipped separately, along with a 15 psig (103 kPa) nitrogen-holding charge in each vessel.

To determine if there are any leaks, the chiller should be charged with refrigerant. Use an electronic leak detector to check all ¯anges and solder joints after the chiller is pres- surized. If any leaks are detected, follow the leak test procedure.

If the chiller is spring isolated, keep all springs blocked in both directions in order to prevent possible piping stress and damage during the transfer of refrigerant from vessel to ves- sel during the leak test process or any time refrigerant is trans- ferred. Adjust the springs when the refrigerant is in operat- ing condition and when the water circuits are full.

Refrigerant Tracer Ð Carrier recommends using an en- vironmentally acceptable refrigerant tracer for leak testing with an electronic detector.

Ultrasonic leak detectors also can be used if the chiller is under pressure.

Do not use air or oxygen as a means of pressurizing the chiller. Some mixtures of HFC-134a and air can un- dergo combustion.

Leak Test the Chiller Ð Due to regulations regarding refrigerant emissions and the difficulties associated with sepa- rating contaminants from refrigerant, Carrier recommends the following leak test procedures. See Fig. 25 for an outline of the leak test procedures. Refer to Tables 5A and 5B for refrigerant pressure/temperature values and to the Pumpout and Refrigerant Transfer Procedures section, page 63.

1.If the pressure readings are normal for the chiller condition:

a.Evacuate the nitrogen holding charge from the ves- sels, if present.

b.Raise the chiller pressure, if necessary, by adding re- frigerant until the pressure is at an equivalent satu- rated pressure for the surrounding temperature. Follow the pumpout procedures in the Pumpout and Refrig- erant Transfer Procedures section, page 63.

Never charge liquid refrigerant into the chiller if the pres- sure in the chiller is less than 35 psig (241 kPa). Charge as a gas only, with the cooler and condenser pumps run- ning, until this pressure is reached, using PUMPDOWN/ LOCKOUT and TERMINATE LOCKOUT mode on the PIC. Flashing of liquid refrigerant at low pressures can cause tube freeze-up and considerable damage.

Run the chiller water pumps whenever transferring, re- moving, or charging refrigerant.

c.Leak test chiller as outlined in Steps 3 - 9.

2.If the pressure readings are abnormal for chiller conditions:

a.Prepare to leak test chillers shipped with refrigerant (Step 2h).

b.Check for large leaks by connecting a nitrogen bottle and raising the pressure to 30 psig (207 kPa). Soap test all joints. If the test pressure holds for 30 minutes, prepare to test for small leaks (Steps 2g - h).

c.Plainly mark any leaks that are found.

d.Release the pressure in the system.

e.Repair all leaks.

f.Retest the joints that were repaired.

g.After successfully completing the test for large leaks, remove as much nitrogen, air, and moisture as pos- sible, given the fact that small leaks may be present in the system. This can be accomplished by following the dehydration procedure, outlined in the Chiller Dehydration section, page 49.

h.Slowly raise the system pressure to the equivalent satu- rated pressure for the surrounding temperature but no less than 35 psig (241 kPa) by adding HFC-134a refrigerant. Proceed with the test for small leaks (Steps 3-9).

3.Check the chiller carefully with an electronic leak detec- tor, or soap bubble solution.

46

Image 46
Contents Start-Up, Operation, and Maintenance Instructions Safety ConsiderationsContents Coupling Maintenance Motor Maintenance Piping Check Relief Devices Inspect WiringOCCPC01S Input Service Congurations Inspect Water PipingContents Abbreviations Introduction17EX Chiller Familiarization Performance CertifiedTypical 17EX Chiller Components OIL Cooling Cycle Lubrication CycleStarters Refrigeration, Cycle17EX Compressor Lubrication Cycle Controls DenitionsPIC Component Panel Location Temperature Sensors See Fig Pressure TransducersMajor PIC Components Panel Locations Processor Sensor Input/Output Module Control Center17EX Controls and Sensor Locations PIC LIDPsio GRD Equip GND ÐTewac PROCESSOR/SENSOR INPUT/OUTPUT Module Psio LID Operation and Menus FigGeneral LID Service Screen YES or no , on or OFF , etc. to select the desired state Override OperationsDefault Screen 17EX LID Menu StructureEquipment Configuration Service TableAlarm History Control TestHgbp Ð Hot Gas Bypass CCNCarrier Comfort Network LIDChws SetpointChwr HgbpExample 1 Ð STATUS01 Display Screen Description Range Units Reference Point Name Alarm HistoryLID Display Data Menu Status SelectExample 3 Ð STATUS03 Display Screen Example 2 Ð STATUS02 Display ScreenMenu Status Example 5 Ð Setpoint Display Screen Example 4 Ð STATUS04 Display ScreenMenu ECW Control Option Example 6 Ð Configuration Config Display ScreenICE Build Termination Example 7 Ð LEAD/LAG Configuration Display Screen LAG =2, Standby =3Example 8 Ð SERVICE1 Display Screen Example 10 Ð SERVICE3 Display Screen Example 9 Ð SERVICE2 Display ScreenSpare Alert Enable Menu ServiceDischarge Temperature Example 11 Ð Maintenance MAINT01 Display ScreenExample 12 Ð Maintenance MAINT02 Display Screen Bearing TemperatureExample 14 Ð Maintenance MAINT04 Display Screen Example 13 Ð Maintenance MAINT03 Display ScreenDescription RANGE/STATUS Units Reference Point Name PIC System Functions Page Protective Safety Limits and Control Settings Capacity Overrides Page Page ECW Cent Capacity ICE Build Setpoint Example of Attach to Network Device Screen To Access the Service Screens Example of Holiday Period ScreenSTART-UP/SHUTDOWN Recycle Sequence FigPage Equipment Required Before Initial START-UPJob Data Required MotorPage 17EX Leak Test Procedures Temperature F Ð HFC-134a Pressure Ð Temperature FÐ HFC-134a Pressure Ð Temperature C Temperature CDehydration Cold Trap Check Optional Pumpout Compressor Water Pip Inspect Wiring900 500 901 7000 1000 7001-14500 2500 External Gear Pre-Start Checks Recommended Motor Fastener Tightening TorquesExternal Gear Lubrication System Mechanical Starters Check StarterSOLID-STATE Starters Input the Design Set Points Ð To modify the set Set Up Chiller Control CongurationInput the Local Occupied Schedule OCCPC01S Surge Limiting or Change the LID Configuration if NecessaryT1/P1 Full Load Points T2/P2 Increase P1 by Decrease P1 by Load Surge Prevention Occurs TOO Soon Occurs TOO Late50% Control Test Menu Functions Charge Refrigerant into ChillerInitial START-UP Tests to be Devices Tested PerformedCheck Motor Rotation Dry Run to Test Start-Up SequenceInitial Motor START-UP Page Flange Nut Tightening Torques Low Speed Couplings Only To Prevent Accidental Start-Up Ð The PIC can be Calibrate Motor Current Demand SettingCheck Oil Pressure and Compressor Stop General RecommendationsStarting the Chiller Operating InstructionsOperator Duties Stopping the ChillerPumpout and Refrigerant Transfer Procedures Operating the Optional Pumpout CompressorPlant Chiller Serial No Chiller Model No Refrigerant Type Rear View RLA Valve ConditionGeneral Maintenance Return Chiller to Normal Operating ConditionsContact Seal Maintenance Refer to Ð Checking Guide Vane Linkage Ð Refer to FigContact Seal Page Chiller Alignment Checking Preliminary AlignmentMeasuring Angular Misalignment Elevation Alignment Formula Adjusting Angular Misalignment in Plan HOT Alignment CheckCorrecting Parallel Misalignment DowelingCheck Safety and Operating Controls Monthly Weekly MaintenanceScheduled Maintenance Changing the Oil Filters17EX Chiller Oil Specications Compressor OILPumpout Typical Float Valve Arrangement Sleeve Bearings Page Motor Riggings Inspect the Heat Exchanger Tubes Troubleshooting Guide Controls for Optional Pumpout CompressorPage MAINT03 MAINT01MAINT02 MAINT04Oilt 1CR AUXOilpd PICStarts Limit Exceeded Autorestart in ProgressPotential FREEZE-UP FaultOperation Failure to StopRunning Ð Temp Control Running Ð Demand LimitedChiller Protect Limit Faults Alert Sensor Fault AlertLOW OIL Pressure Autorestart PendingDESCRIPTION/MALFUNCTION Probable CAUSE/REMEDY Possible Cause Ð Item NO.s External Gear Troubleshooting GuideProblem Possible Cause ActionÐ Thermistor Temperature F vs Resistance/Voltage Drop Temperature Voltage Resistance DropÐ Thermistor Temperature C vs Resistance/Voltage Drop Temperature Voltage Resistance DropModule Address Module SwitchControl Modules Input Options ModuleStarter Management Module SMM Fig Processor/Sensor Input/Output Module Psio FigGRD Four-In/Two-Out Module Fig Installation of NEW Psio ModuleSwitch Setting Options Module Options ModulePhysical Data and Wiring Schematics 4-In/2-Out ModuleCondenser Total Weight Condenser Charge Additional Cooler WeightsWeight Vessel SIZE² 100Drive Component Weights Additional Condenser WeightsCompressor Weight and Elbow Weight 101Ð Total Motor Weight, SI kg Ð Total Motor Weight, English lb102 Approximate Refrigerant HCFC-134a Charge Marine Waterbox Cover WeightsNIH Waterbox Cover Weights 103Relief Valve Locations and Data Auxiliary Systems, Electrical Data104 Compressor Fits and Clearances 105Clearance Type Description 106Measure 107 Tabulation Ð Impeller Clearances Open-Drive Compressors17FX 108 Press 109Temp Tewac110 111 112 113 GeneralT1-T4 114GND Ð Ground Terminal StripIndex Index Index Index Index Copyright 1997 Carrier Corporation

17EX specifications

The Carrier 17EX is recognized as an innovative air conditioning solution that combines efficiency with advanced technology. This model is designed to meet the increasing demands of residential and commercial cooling needs while maintaining environmental consciousness.

One of the standout features of the Carrier 17EX is its impressive Seasonal Energy Efficiency Ratio (SEER) rating. With a SEER rating that often exceeds 17, this unit ensures optimized energy consumption, significantly lowering operational costs for users. The incorporation of advanced compressor technology allows the system to adjust its cooling output based on the specific needs of the environment, thus providing both comfort and energy savings.

The Carrier 17EX utilizes a variable-speed inverter-driven compressor that enhances its performance and adaptability. This technology allows the air conditioning unit to operate at different speeds, intelligently adjusting to changing load conditions. As a result, the system runs more efficiently and quietly, providing a more consistent comfort level without the abrupt temperature swings associated with traditional units.

In addition to efficiency, the Carrier 17EX also prioritizes reliability and durability. The unit comes with a robust cabinet that protects the components from weather elements, ensuring longevity and consistent performance. The innovative design integrates a corrosion-resistant finish and robust insulation, which further enhances the unit's resilience in various environmental conditions.

For users concerned about indoor air quality, the Carrier 17EX includes advanced filtration systems designed to capture allergens and airborne particles. This feature is particularly beneficial for individuals with respiratory issues, ensuring that the air circulated within the space is clean and healthy.

Moreover, the Carrier 17EX is equipped with smart technology capabilities, allowing users to control their systems remotely through smartphones or other smart devices. This connectivity not only provides convenience but also empowers homeowners to optimize their energy use by adjusting settings on the fly, ensuring efficient operation even when they are away from home.

Overall, the Carrier 17EX stands out in the marketplace for its exceptional energy efficiency, advanced technology, and commitment to providing reliable and effective cooling solutions. Its combination of modern features makes it a preferred choice for those looking to enhance comfort while being mindful of energy consumption and environmental impact.