HP Performance Optimized Data Center (POD) 40c manual Drainage, Chilled water supply

Page 13

Requirement

Specification

 

 

 

 

 

Connection

1.9 cm (.75 in) G

 

 

 

Adapter to 1.9 cm (.75 in) FPS

 

Hardness

No greater than 40°fH (equal to 400 ppm of CaCO3)

 

Conductivity

100 to 1250 μS/cm

 

Organic compounds

None

 

Type of water

Drinking water. Do not use de-mineralized or softened water.

 

Instant water fill flow

0.6 lpm (0.16 gpm)

 

rate

 

 

Humidifier

For the exact requirements, see the humidifier documentation.

 

 

 

 

 

IMPORTANT: If your water is out of range, consult a water quality expert.

IMPORTANT: You must provide a humidification water supply isolation valve that is external to the HP POD 40c G2.

In addition to the previous requirements, observe the following requirements and recommendations:

Do not treat the water with softeners. Softeners can produce foam, which affects the operation of the unit.

Do not use well water, industrial water, water from cooling circuits, or water contaminated by any chemicals or bacteria.

Do not add potential irritants to the water, such as disinfectants or anti-corrosive compounds.

The manufacturer recommends installing an in-line filter for the water supply. It is your responsibility to determine if a filter should be installed, and if so, its location. The filter cannot be installed inside the HP POD 40c G2 and must be compatible with the type of humidifier that is installed.

For more information, see the HP Performance Optimized Datacenter 40c G2 Maintenance and Service Guide.

Drainage

Requirement

Location

Specification

 

 

 

Condensate drains

Hot aisle side (2)

3.18 cm (1.25 in) drain line and 26.5 lpm (7 gpm) max

Humidifier drains

Cold aisle side (1)

3.18 cm (1.25 in) drain line and 26.5 lpm (7 gpm) max

Chilled water supply

The following are the water quality requirements and specifications:

Closed-loop water must not contain any lime scale deposits or loose debris.

The temperature of the chilled water supplied to the HP POD 40c G2 must be 12ºC to 24ºC (55ºF to 75ºF).

CAUTION: Freezing water can cause a blockage and damage to the unit. In outside locations that are subject to freezing temperatures, an additive such as glycol might be necessary to lower the freezing point. However, since the heat transfer potential of water with glycol is lower, the HP POD 40c G2 must be de-rated accordingly.

Site requirements 13

Image 13
Contents Part Number August Edition AbstractPage Contents Appendix C Regulatory compliance notices HP POD 40c G2 site assessment checklistOverview Safety and NEC complianceAbout this document Site assessment Site safety and securitySite preparation Fire detection and suppressionHP POD 40c G2 capacities Electrical power capacities critical IT powerHP POD 40c G2 capacity limitations Overall system capacitiesDimensions and clearances HP POD 40c G2 weightSite requirements Site padSite requirements Safety and clearance area Future expansions Grounding requirementsUtilities Grounding feature SpecificationHumidifier water supply Requirement Location Specification Requirement SpecificationDrainage Chilled water supply10-2500 µmhos Electrical power system configuration Power infrastructure installationPiping materials Site electrical systemTransformers and switchboards Environmental control system Supported facility connectionsAdditional POD connections Connection portalsDemarcation box Fire box Humidifier Fire, safety, and security notificationsHP POD 40c G2 security G2 is shut down Environmental considerations Areas prone to lightning or power surgesEnvironmental risks Cold weatherCompleting a site assessment Site plan requirements and actionsHP Site Preparation Drawing Package Zoning and permit requirementsSite planning HP POD 40c G2 installationHP POD 40c G2 storage requirements Assembly equipment locationsSite plan requirements and actions Appendix a HP site assessment HP POD 40c G2 site assessment checklistAs stated by the site engineering personnel can be Description Sign-offExisting or planned supply/return headers Security Customer responsibilities Description Sign-offProvide assistance in instances where a temporary Installation prerequisites HP POD 40c G2 site readiness checklistAppendix B Preparing for delivery Pre-delivery tasksWhen installing on an elevated surface, verify that General water supply Description Sign-off Power requirements Description Sign-offChilled water system Description Sign-off General Description Sign-offDescription Sign-off HP POD 40c G2 regulatory compliance Appendix C Regulatory compliance noticesRegulatory compliance identification numbers Federal Communications Commission noticeCanadian notice Avis Canadien CablesGlossary North American Uninterruptible power systemVery early smoke detection apparatus Documentation feedback Index Index