HP Performance Optimized Data Center (POD) 40c manual General water supply Description Sign-off

Page 33

Item

Description

Sign-off

 

 

 

 

 

28

Verify the location of the EPO system external to the

 

 

 

powerhouses, if applicable.

 

 

29

Verify the location of the remote electronic monitoring system.

 

 

30

Verify that tie-downs and other AHJ-required facilities for the HP

 

 

 

POD 40c G2 and power containers are complete at least one

 

 

 

week prior to arrival of HP-provided equipment.

 

 

General water supply

 

 

 

 

 

Item

Description

Sign-off

 

 

 

 

 

1

Verify that the site drainage is complete, and the HP POD 40c

 

 

 

G2 is not in a drainage path or flood prone area. HP

 

 

 

recommends placing the HP POD 40c G2 on a raised site pad

 

 

 

to prevent water from entering the HP POD 40c G2.

 

 

2

Verify that the humidification water quality meets or exceeds

 

 

 

these standards, which are essentially drinking water

 

 

 

standards.

 

 

3

Verify the humidification water supply isolation valve is

 

 

 

installed for each POD.

 

 

Chilled water system

 

 

 

 

 

Item

Description

Sign-off

 

 

 

 

 

1

Verify the chilled water supply and return headers are

 

 

 

accessible, in the appropriate location, and 100 cm (4 in) in

 

 

 

diameter.

 

 

2

Verify that the chilled water supply temperature meets the

 

 

 

minimum POD chilled water supply temperature of 10°C

 

 

 

(50°F).

 

 

3

Verify that a sufficient chilled water flow rate is available.

 

 

4

If necessary, verify that the customer-required chilled water

 

 

 

return temperatures can be attained.

 

 

Power requirements

 

 

 

 

 

Item

Description

Sign-off

 

 

 

 

 

1

Verify that the short circuit analysis, arc flash, and circuit

 

 

 

breaker coordination studies are complete. Verify power work

 

 

 

is completed according to the approved conduit routing

 

 

 

drawings that show the exact routes, plan view, sections, and

 

 

 

elevations.

 

 

2

Verify that temporary site power for installation and

 

 

 

construction is planned and available, if applicable.

 

 

3

Verify that adequate site power exists per the HP POD 40c G2

 

 

 

requirements.

 

 

General

 

 

 

 

 

Item

Description

Sign-off

 

 

 

 

 

1

Verify the utility connection to the HP POD 40c G2 and any

 

 

 

required metering equipment.

 

 

2

Verify the third-party commissioning services that might be

 

 

 

required by the owner.

 

 

 

 

Appendix B: Preparing for delivery 33

Image 33
Contents Part Number August Edition AbstractPage Contents Appendix C Regulatory compliance notices HP POD 40c G2 site assessment checklistSafety and NEC compliance OverviewAbout this document Site assessment Site safety and securitySite preparation Fire detection and suppressionHP POD 40c G2 capacities Electrical power capacities critical IT powerHP POD 40c G2 capacity limitations Overall system capacitiesDimensions and clearances HP POD 40c G2 weightSite requirements Site padSite requirements Safety and clearance area Future expansions Grounding requirementsGrounding feature Specification UtilitiesHumidifier water supply Requirement Location Specification Requirement SpecificationDrainage Chilled water supply10-2500 µmhos Electrical power system configuration Power infrastructure installationPiping materials Site electrical systemTransformers and switchboards Environmental control system Supported facility connectionsAdditional POD connections Connection portalsDemarcation box Fire box Fire, safety, and security notifications HumidifierHP POD 40c G2 security G2 is shut down Environmental considerations Areas prone to lightning or power surgesEnvironmental risks Cold weatherCompleting a site assessment Site plan requirements and actionsHP Site Preparation Drawing Package Zoning and permit requirementsSite planning HP POD 40c G2 installationHP POD 40c G2 storage requirements Assembly equipment locationsSite plan requirements and actions Appendix a HP site assessment HP POD 40c G2 site assessment checklistAs stated by the site engineering personnel can be Description Sign-offExisting or planned supply/return headers Security Customer responsibilities Description Sign-offProvide assistance in instances where a temporary Installation prerequisites HP POD 40c G2 site readiness checklistAppendix B Preparing for delivery Pre-delivery tasksWhen installing on an elevated surface, verify that General water supply Description Sign-off Power requirements Description Sign-offChilled water system Description Sign-off General Description Sign-offDescription Sign-off HP POD 40c G2 regulatory compliance Appendix C Regulatory compliance noticesRegulatory compliance identification numbers Federal Communications Commission noticeCanadian notice Avis Canadien CablesGlossary Uninterruptible power system North AmericanVery early smoke detection apparatus Documentation feedback Index Index
Related manuals
Manual 84 pages 34.53 Kb

Performance Optimized Data Center (POD) 40c specifications

The HP Performance Optimized Data Center (POD) 40c is a state-of-the-art data center solution designed to meet the increasing demands for efficiency, scalability, and flexibility in enterprise environments. Aimed at delivering high-performance computing with minimal environmental impact, the POD 40c integrates innovative technologies and features to optimize operations.

One of the standout characteristics of the POD 40c is its modular design, allowing for easy deployment and scalability. Customers can configure their data center according to specific requirements, enabling rapid expansion as business needs evolve. The POD can house up to 240 servers, providing ample capacity to support intensive workloads while ensuring that users can quickly adapt to changing technological landscapes.

The energy efficiency of the POD 40c is a significant highlight. By employing advanced cooling technologies, including hot aisle/cold aisle containment and direct expansion cooling, it minimizes energy consumption while maintaining optimal temperatures for hardware components. This focus on efficiency also extends to power management, with redundant power supplies and the integration of high-efficiency power distribution units (PDUs) that help reduce operational costs.

In terms of connectivity, the HP POD 40c is equipped with comprehensive networking capabilities. The design includes integrated cabling systems that ensure organized and efficient routing of power and data. This dedication to streamlined connectivity facilitates faster data transfer rates and decreases latency, enhancing overall system performance.

Moreover, security is a paramount consideration in the POD 40c design. The unit incorporates various security features, including access controls, environmental monitoring, and surveillance options, which provide peace of mind for data-sensitive businesses. These elements work together to ensure that critical data remains protected from unauthorized access and environmental threats.

Sustainability is another key aspect, as the POD 40c is designed to be environmentally friendly. The system's effective cooling mechanisms and efficient power usage contribute to reduced carbon emissions, aligning with corporate sustainability goals and industry regulations.

In conclusion, the HP Performance Optimized Data Center (POD) 40c represents a cutting-edge solution for modern data center requirements. Its modularity, energy efficiency, robust connectivity, enhanced security, and sustainability make it an attractive option for organizations aiming to optimize their IT infrastructure while maintaining agility in a rapidly evolving digital landscape. The POD 40c exemplifies HP's commitment to providing innovative and performance-driven data center solutions, positioning it as a transformative asset for businesses seeking to thrive in a data-driven world.