Item | Description | |
|
|
|
7 | When installing on an elevated surface, verify that the |
|
| maximum height requirements for the circuit breaker actuator |
|
| meet the local and national requirements. Verify that proper |
|
| landings and the catwalk are planned for electrical cabinet |
|
| access. |
|
8 | Verify the planning for required egress routes for all HP POD |
|
| 40c G2 personnel doors, cargo doors, and service area doors, |
|
| including landings, the catwalk, and stairs. |
|
9 | Verify that the local AHJ is contacted, all applicable codes and |
|
|
| |
| permits are obtained. |
|
10 | Verify that the site location has clearances for the HP POD 40c |
|
| G2 installation, including any permanent structures, such as |
|
| fences, walls, vestibules, and buildings. |
|
11 | Verify that all utilities, overhead and underground, are |
|
| identified to maintain required clearance. |
|
12 | Verify that there is adequate clearance around the HP POD 40c |
|
| G2 for door operation, installation, and maintenance |
|
| equipment. |
|
13 | Verify that the site location and site pads are marked for any |
|
| transformer, external switchboard, generators, and |
|
| powerhouses. |
|
14 | Verify that the site has provisions for proper grounding and that |
|
| the site location includes a grounding electrode system. |
|
15 | Verify that the site location has adequate lighting for the HP |
|
| POD 40c G2 installation. |
|
16 | Verify that a truck and equipment staging areas are identified. |
|
17 | Verify the location for the fuel tanks for generators, |
|
| powerhouses, and other equipment, if applicable. |
|
18 | Verify the locations for cranes |
|
| HP POD 40c G2 installation. |
|
19 | Verify site access and clearances for equipment, including the |
|
| crane and forklifts. A clear path to the site must be maintained |
|
| with clearance for all gates, headers, utility lines, and so on. |
|
20 | Verify that the locations for storage and trash disposal are |
|
| identified. |
|
21 | Verify that the safety equipment is planned for and in place in |
|
| accordance with the customer’s site safety program. |
|
22 | Verify the site interfaces and locations to connect the fire alarm, |
|
| security system, and communication system to the HP POD 40c |
|
| G2. This ensures that the POD can be properly connected to the |
|
| site BMS. |
|
23 | Verify that proper disposal methods are used for existing or |
|
| potentially contaminated and/or hazardous materials. |
|
24 | Verify the availability of security systems or equipment, |
|
| including site fences, required after construction. |
|
25 | Verify the availability of temporary facilities associated with the |
|
| relocation of existing services and operations. |
|
26 | Verify that all work relating to soil testing, removal, and that site |
|
| remediation is complete. |
|
27 | Verify that a temporary or permanent load bank is available, if |
|
| applicable. |
|
Appendix B: Preparing for delivery 32