HP Performance Optimized Data Center (POD) 40c manual

Page 32

Item

Description

Sign-off

 

 

 

7

When installing on an elevated surface, verify that the

 

 

maximum height requirements for the circuit breaker actuator

 

 

meet the local and national requirements. Verify that proper

 

 

landings and the catwalk are planned for electrical cabinet

 

 

access.

 

8

Verify the planning for required egress routes for all HP POD

 

 

40c G2 personnel doors, cargo doors, and service area doors,

 

 

including landings, the catwalk, and stairs.

 

9

Verify that the local AHJ is contacted, all applicable codes and

 

 

site-specific location guidelines are reviewed, and all required

 

 

permits are obtained.

 

10

Verify that the site location has clearances for the HP POD 40c

 

 

G2 installation, including any permanent structures, such as

 

 

fences, walls, vestibules, and buildings.

 

11

Verify that all utilities, overhead and underground, are

 

 

identified to maintain required clearance.

 

12

Verify that there is adequate clearance around the HP POD 40c

 

 

G2 for door operation, installation, and maintenance

 

 

equipment.

 

13

Verify that the site location and site pads are marked for any

 

 

transformer, external switchboard, generators, and

 

 

powerhouses.

 

14

Verify that the site has provisions for proper grounding and that

 

 

the site location includes a grounding electrode system.

 

15

Verify that the site location has adequate lighting for the HP

 

 

POD 40c G2 installation.

 

16

Verify that a truck and equipment staging areas are identified.

 

17

Verify the location for the fuel tanks for generators,

 

 

powerhouses, and other equipment, if applicable.

 

18

Verify the locations for cranes off-loading and operation during

 

 

HP POD 40c G2 installation.

 

19

Verify site access and clearances for equipment, including the

 

 

crane and forklifts. A clear path to the site must be maintained

 

 

with clearance for all gates, headers, utility lines, and so on.

 

20

Verify that the locations for storage and trash disposal are

 

 

identified.

 

21

Verify that the safety equipment is planned for and in place in

 

 

accordance with the customer’s site safety program.

 

22

Verify the site interfaces and locations to connect the fire alarm,

 

 

security system, and communication system to the HP POD 40c

 

 

G2. This ensures that the POD can be properly connected to the

 

 

site BMS.

 

23

Verify that proper disposal methods are used for existing or

 

 

potentially contaminated and/or hazardous materials.

 

24

Verify the availability of security systems or equipment,

 

 

including site fences, required after construction.

 

25

Verify the availability of temporary facilities associated with the

 

 

relocation of existing services and operations.

 

26

Verify that all work relating to soil testing, removal, and that site

 

 

remediation is complete.

 

27

Verify that a temporary or permanent load bank is available, if

 

 

applicable.

 

Appendix B: Preparing for delivery 32

Image 32
Contents Abstract Part Number August EditionPage Contents HP POD 40c G2 site assessment checklist Appendix C Regulatory compliance noticesAbout this document Safety and NEC complianceOverview Site safety and security Site assessmentSite preparation Fire detection and suppressionElectrical power capacities critical IT power HP POD 40c G2 capacitiesHP POD 40c G2 capacity limitations Overall system capacitiesHP POD 40c G2 weight Dimensions and clearancesSite requirements Site padSite requirements Safety and clearance area Grounding requirements Future expansionsHumidifier water supply Grounding feature SpecificationUtilities Requirement Specification Requirement Location SpecificationDrainage Chilled water supply10-2500 µmhos Power infrastructure installation Electrical power system configurationPiping materials Site electrical systemTransformers and switchboards Supported facility connections Environmental control systemAdditional POD connections Connection portalsDemarcation box Fire box HP POD 40c G2 security Fire, safety, and security notificationsHumidifier G2 is shut down Areas prone to lightning or power surges Environmental considerationsEnvironmental risks Cold weatherSite plan requirements and actions Completing a site assessmentHP Site Preparation Drawing Package Zoning and permit requirementsHP POD 40c G2 installation Site planningAssembly equipment locations HP POD 40c G2 storage requirementsSite plan requirements and actions HP POD 40c G2 site assessment checklist Appendix a HP site assessmentDescription Sign-off As stated by the site engineering personnel can be Customer responsibilities Description Sign-off Existing or planned supply/return headers SecurityProvide assistance in instances where a temporary HP POD 40c G2 site readiness checklist Installation prerequisitesAppendix B Preparing for delivery Pre-delivery tasksWhen installing on an elevated surface, verify that Power requirements Description Sign-off General water supply Description Sign-offChilled water system Description Sign-off General Description Sign-offDescription Sign-off Appendix C Regulatory compliance notices HP POD 40c G2 regulatory complianceRegulatory compliance identification numbers Federal Communications Commission noticeCables Canadian notice Avis CanadienGlossary Very early smoke detection apparatus Uninterruptible power systemNorth American Documentation feedback Index Index