method to supply warm air is your responsibility. HP will advise on warm air alternatives; however, all references to warm air production are your responsibility during this procedure.
Cold weather power up checklist
Site electrical
•Verify that all site POD critical IT feeder supply breakers are open.
•Verify that all site Adiabatic mechanical feeder supply breakers are open. POD electrical
•Service
•Hot
IMPORTANT: Following these steps prevent any possibility of energizing the IT load.
•IT sections A and B:
a.Close all
b.Close and latch the control cabinet.
c.Position the EPO system (on page 19) to Armed (white) or Bypass (green).
d.Verify that all EPO activation buttons are in the reset position (not depressed).
•IT critical power feed cabinets A and B:
a.Close all
b.Close and lock electrical cabinet doors.
c.Close all Adiabatic power supply feeder breakers in both the primary mechanical and secondary mechanical cabinets.
d.Close and lock Adiabatic primary mechanical and secondary mechanical cabinets.
Standard power up procedure
Perform the following procedures in the exact order in which they are listed.
Electrical
Site electrical
1.Close all site POD critical IT power feeder supply breakers and monitor them for any effects that are not standard.
2.Close all site Adiabatic mechanical feeder supply breakers and monitor them for any effects that are not standard.
POD electrical
Close all of the site Adiabatic unit service disconnects in the service aisle.
Maintenance 81