Thermo Products OL6FA072DV5(B/R), OL6RA072D48(B/R), OL6FA072D48(B/R) C. Operating Modes

Page 36

EAC (electronic air cleaner)

The control provides a 120 VAC output for an electronic air cleaner. This output is energized whenever the fan motor is energized (either low, heat or cool speed). Connection is made via male quick connect terminal labeled “EAC”.

Humidifier

The control provides a 120 VAC output for a humidifier. Connections are made to a male quick connect terminal labeled “FAN”.

Status LED

A red LED is provided to indicate any thermostat input has been recognized by the microprocessor on the control. See Diagnostic Features for a function description of operation.

Thermostat Input LEDs

Four green LEDs are placed beneath their respective thermostat connections (W, Y, G and DEHUM) and operate whenever a call is present. See Diagnostic Features for a function description of operation.

C. Operating Modes

Standby Mode

All outputs are off and the control is waiting for a thermostat demand. The thermostat inputs, and limit switch are continuously monitored. The control initiates action when a thermostat call is received or limit switch opens.

Fan Mode

A call for fan (“G”) is received from the thermostat. If no other mode is calling for blower operation, the control will operate the fan relay (K4) and power the “Low” blower speed terminal. The fan mode will be operated as long as the “G” input is calling and neither the Heat mode nor the Cool mode is calling for blower operation. When the Heat and Cool modes call for blower operation, their respective outputs will take precedence after their respective turn-on time delays have expired.

Cooling Mode

A call for cool (“Y”) is received from the thermostat. If the heat mode is not active or the anti-short cycle delay is not in effect, the control will energize the “CC” terminal and after a 10 second power demand conservation delay energizes the “COOL” speed blower terminal.

When the call for cool is satisfied, the “CC” terminal is de-energized and the cooling off delay of 45 seconds is started. Forty-five seconds later the “COOL” speed blower terminal is de-energized and the control reverts to Standby Mode.

Dehumidification Operation

If a call for dehumidification is received while the Cool Mode is active, blower speeds will be reduced. The PSC “COOL” blower speed terminal (1158-100 model only) will be de-energized and “Low” blower speed will be energized.

Anti-Short Cycle Operation

To prevent compressor short cycling, a call for cooling will be ignored for four minutes after the termination of any cooling call. The anti-short cycle delay is also in effect at power-up.

33

Image 36
Contents OL6RA072D48B/R OL6FA072D48B/ROL6RA072DV5B/R OL6RX072DV5RCONTENTS Configuration FeatureModel Number Digit FuelI. SAFETY SECTION cWARNING AND CAUTIONScCAUTION DO NOT ATTEMPT TO START THE BURNER WHEN 1.Excess oil has accumulatedPage A. CODES AND CLEARANCES a. Combustible materialb. Non-combustiblematerial A. CHIMNEY TYPE OFFROM MODEL NO1. PROPER CHIMNEY SIZE 2. PREVENTION OF CHIMNEY CONDENSING4. PROPER VENT CONNECTOR PIPE/CHIMNEY CONNECTION 3. PROPER CHIMNEY HEIGHT7. TIGHT CLEAN-OUTDOORS AND CONNECTIONS 6. TIGHT JOINTS8. NO INTERCONNECTED CHIMNEY FLUES 9 FLUE PIPE CLEARANCES, SIZING AND TYPEB. VENTING ROTATION OF FRONT FLUE ELBOW C. DRAFT REGULATORSNote Do not use with Direct Vent application D. DUCT WORK/AIR CONDITIONING Airflow Requirements and Sizing of Duct WorkPage The ASHRAE Handbook - Fundamentalsis an excellent source of duct system design principles and pressure drop data. Conversely, for a specified type of fitting, it is also possible to determine the required size or diameter of the component for a specified pressure drop and flow rate 1.HEATING CFM HEAT OUTPUT OF FURNACE BTUH 1.1 X TR TEMPERATURE RISE, F = HEATINGCFME. Air Filters Mounted Internal to Furnace MaximumModel Number Filter TypeF. LIMIT POSITION AND LOCATION G. BURNER INSTALLATION DO NOT CHANGE POSITION OF THE CHAMBERH. BURNER SPECIFICATIONS AND APPLICATIONS OIL NOZZLE CAPACITY CHART+ INSULATOR S = SLEEVE OR N = NONE NOZZLE SIZE2 STAGE FIRING RATES CAPACITYFIRING NOZZLE SIZEMOUNTING THE 2-STAGERIELLO BURNER I. OIL TANK AND PIPING5.A readily accessible, design-certified,manual oil shutoff valve, with a non-displaceablerotor member, shall be installed in the fuel oil supply piping within 6 feet of the appliance J. OIL FILTER K. ELECTRICAL WIRIINGAssembly MaximumWire size selections in Table 10 are based upon Table 310-16of the National Electrical Codefor three copper conductors, with insulation rated for 75 degrees Celsius, contained in raceway at 30 degrees Celsius. For other wire insulation temperature ratings and ambient conditions, refer to the National Electrical Codefor the minimum wire sizing requirements Thermostat Anticipator Setting Preferred method of adjustment L. Blower Motor Speed Selection Heating Speed Set-ups OL6*A072DV5Furnace Motor Current Draw Amps/ / Watts vsLOW CAPACITY HIGH CAPACITY= Recommended heating speed setting Heating Speed Set-ups 2 - Stage OL6*X072DV5Cooling Speed Set-ups OL6**072DV5 Furnace Motor CurrentDraw Amps / Watts vs External Static Pressure in W.CPage M. BLOWER CONTROLLER INFORMATION FOR PSC MOTOR TERMINAL DEFINITIONS & FIELD WIRINGA. Inputs B. OutputsC. Operating Modes Heat Mode PSC TROUBLE SHOOTING DIAGNOSTIC FEATURESN. STARTUP PROCEDURES Operating InstructionsFor Your Safety Read Before Operating i.STOP! Read the safety information above2. Adjustment of Burner Combustion To Turn Off Oil to ApplianceCOMBUSTION HEAD SETTING FOR 2-STAGERIELLO BURNER AIR DAMPER ADJUSTMENT TURN TO THE RIGHT SIGN +TURN TO THE LEFT SIGN 1st STAGE ADJUSTMENT 2nd STAGE ADJUSTMENT3. Adjustment Of Heat Input Rate Notice Minimum return air temperature is 55F4. Setting Supply Air Temperature Rise 5. Checkout Procedure III. USERS INFORMATION SECTION C. INSPECTION AREAScCAUTION DO NOT ATTEMPT TO MAKE REPAIRS YOURSELF cCAUTION DO NOT ATTEMPT TO START THE BURNER WHENE. FILTER CLEANING AND LOCATION D. STARTING THE BURNERIV. INSTALLERS INSTRUCTIONS TO USER V. DEALER MAINTENANCE A.GENERAL INSPECTIONSAFETY DURING SERVICING AND INSPECTION C. HEAT EXCHANGER CLEANING INSTRUCTIONS B. HEAT EXCHANGERFigure 24 Heat Exchanger Clean-Outs Vacuum Hose Length OL6 8FTFilter maintenance procedure D. ELECTRICAL SYSTEME. SUPPLY/RETURN AIR BLOWER F. SUPPLY/RETURN AIR FILTERFilter replacement G. EXTENDED APPLIANCE SHUTDOWNON STARTUP 2.Remove the furnace front door Beckett Burner Riello BurnerVII. TROUBLESHOOTING A. DIAGNOSTICSDiagnostic Features PERSONNEL, AND NOT BY THE FURNACE OWNERB. CAD CELL CHECKOUT PROCEDURE VIII. Sequence of Operations Flow Chart Page IX. Trouble Shooting Flow Chart Page Page Page Page CUSTOMER HEATINGSYSTEM Appendix - A Replacement Parts Replacement Parts for OL6F*072DPage Replacement Parts for OL6R*072D Page Appendix - B Wiring Diagrams OL6*A072D48 PSC Wiring DiagramOL6*A072DV5 ECM Wiring Diagram OL6*X072DV5 ECM 2-StageWiring Diagram