Stovax Studio 22 manual Arrangement of Fuel BED

Page 25

INSTALLATION INSTRUCTIONS

INSTALLATION

9.3Remove the screw from the pressure test point

Connect a suitable pressure gauge to the test point located on the inlet fitting

Refit the burner

Turn on the gas

Light the appliance to check for leaks

Turn off the gas

Remove the burner

Disconnect the pressure test point

Replace the test point screw

9.4• Replace the access panel in the base of the appliance with the two screws, Diagram 34, Arrow B

Replace the rear air baffle, securing each side with the two screws, Diagram 34 Arrow A

34

A

 

 

A

B

AR2116

 

Put the burner tray in place and tighten the four screws

Replace the vermiculite back panel

Refit the two side panels

Refit the clips to the upper inside to hold the side panels in place, Diagram 35

Refit the front vermiculite panel in front of the burner

35

Vermiculite side panel

10. ARRANGEMENT OF FUEL BED

ADVICE ON HANDLING AND DISPOSAL OF FIRE CERAMICS

The fuel effect and side panels in this appliance are made from Refractory Ceramic Fibre (RCF), a material which is commonly used for this application.

Protective clothing is not required when handling these articles, but we recommend you follow normal hygiene rules of not smoking, eating or drinking in the work area and always wash your hands before eating or drinking.

To ensure that the release of RCF fibres are kept to a minimum, during installation and servicing a HEPA filtered vacuum is recommended to remove any dust accumulated in and around the appliance before and after working on it.

When servicing the appliance it is recommended that the replaced items are not broken up, but are sealed within heavy duty polythene bags and labelled as RCF waste.

RCF waste is classed as stable, non-reactive hazardous waste and may be disposed of at a licensed landfill site.

Excessive exposure to these materials may cause temporary irritation to eyes, skin and respiratory tract; wash hands thoroughly after handling the material.

After cleaning the fire or replacing parts, carefully re-assemble the ceramic components. WHEN THE EMBERS

ARE PLACED ON THE BURNER IT IS IMPORTANT THEY DO NOT COVER ANY PORTS!

The fuel bed is made up of embers and 6 logs, identifiable by moulded letters:

10.1Place the embers around the burner holes as shown in Diagram 36. Do not cover any of the holes.

36

AR2120

10.2Place Log A onto the two studs on the burner skin,

Diagram 37, with charred effect of the log facing forward.

AR2127

25

Image 25
Contents Studio Studio 22 Balanced flue 8704BFLEC P8704BFLEC Covering the Following ModelFail FLUE CHECKGAS CHECK Increasing Temperature MAN ModeDecreasing Temperature GeneralTimer Mode Temp ModeLOW Battery Setting the TimeChanging the Studio Batteries Cleaning the StudioAll models Arrangement of Fuel BED Advice on Handling and Disposal of Fire CeramicsFire will not Light HOT SURFACESCovering the Following Models Technical SpecificationStudio 22 BF 8704BFLEC P8704BFLEC CATQty Description Fixing Kit containing Packing ChecklistProfil Frame Dimensions Size mm Steel Frame Dimensions Size mmBauhaus Frame Dimensions Size mm Flue and Chimney Requirements SITE REQUIREMENTSRear Exit Flue OptionsTOP Exits TOP Flue UP & OUT KITTOP Flue Vertical Offset KIT 8530/8530AN TOP Flue Vertical KIT 8524/8524ANExtra Flue Lengths GAS SupplyAppliance Location Safety Precautions InstallationInstallation of the appliance AR2117 Distance to Combustible Material Stud Work InstallationSlips Flue system see Installation, Flue AssemblyApply a plaster finish to the chimney breast Studwork for Cool Wall Installation KIT Flue Assembly MAX Wall Thickness MINTOP Exit Vertical & Horizontal Flue TOP Exit Vertical Including OffsetAdd 10 mm to the outlet end Assembling the ApplianceArrangement of Fuel BED AR02123 Lighting the Studio Thermostatic Remote ControlCommissioning CommissioningSymptom Cause Remedy Servicing / Fault Finding ChartsServicing Requirements CheckFlame Failure Functional Check Ignition Functional CheckWindow Frame Assembly Replacing PartsGeneral Decorative FrameVermiculite Panels MaIN Control AssemblyMaIN Burner Pilot Burner Bracket Pilot Unit AssemblyElectrode GAS Valve Ignition LeadPilot Injector ThermocoupleControl BOX Magnetic safety valveMain injector Primary Aeration PlateFollow , Main Control Assembly Pressure and Leak Testing the ApplianceComponent Short Spares List Studio3RD Service 1ST Service5TH Service 7TH ServiceMember of the Stovax Group