SERVICING INSTRUCTIONS

REPLACING PARTS

1.GENERAL

1.1All main components can be replaced without removing the appliance from its installation. It is essential that the gas supply to the appliance is turned off at the isolation device before proceeding further.

1.2DISCONNECT BATTERIES BEFORE SERVICING THE

APPLIANCE

1.3Removal of Flue

If, for any reason, the flue has to be removed from the appliance, the seal must be replaced in the inner spigot.

1.4Access to the controls is restricted and the whole of the control assembly is to be removed as one unit. Refer to

Section 7 below

2.DECORATIVE FRAME

2.1The same method is used to remove each frame.

Lift the frame upwards off the four support brackets,

Diagram 1

1

AR2136

NOTE: THE STEEL FRAME IS HEAVY. TAKE CARE WHEN LIFTING

3.WINDOW FRAME ASSEMBLY

3.1Using the allen key provided to release the upper and lower catches on the right side of the door:

Slide the allen key into the gap between the door and frame and locate the catch of the upper lock

Push the allen key DOWN

Slide the allen key into the gap and locate the lower lock

Push the allen key UP

Open the door outwards

When closing the door ensure the door catches are fully engaged.

2

AR2119

3.2To completely remove the glass front:

Open the door at a right angle to the fire

Lift the door vertically off its hinges and place to one side, Diagram 3

3

AR2137

Refit in reverse order

Refit in reverse order

4.GLASS WINDOW

4.1Remove the two clips and brackets from either side of the frame, Diagram 4

4

AR1864

Lift the glass clear from the lock bracket at the top of the frame and slide out

31

Image 31
Contents Studio Studio 22 Balanced flue 8704BFLEC P8704BFLEC Covering the Following ModelFail FLUE CHECKGAS CHECK General MAN ModeIncreasing Temperature Decreasing TemperatureSetting the Time Temp ModeTimer Mode LOW BatteryChanging the Studio Batteries Cleaning the StudioAll models Arrangement of Fuel BED Advice on Handling and Disposal of Fire CeramicsFire will not Light HOT SURFACESCAT Technical SpecificationCovering the Following Models Studio 22 BF 8704BFLEC P8704BFLECQty Description Fixing Kit containing Packing ChecklistProfil Frame Dimensions Size mm Steel Frame Dimensions Size mmBauhaus Frame Dimensions Size mm Flue and Chimney Requirements SITE REQUIREMENTSTOP Flue UP & OUT KIT Flue OptionsRear Exit TOP ExitsGAS Supply TOP Flue Vertical KIT 8524/8524ANTOP Flue Vertical Offset KIT 8530/8530AN Extra Flue LengthsAppliance Location Safety Precautions InstallationInstallation of the appliance AR2117 Distance to Combustible Material Stud Work InstallationSlips Flue system see Installation, Flue AssemblyApply a plaster finish to the chimney breast Studwork for Cool Wall Installation KIT Flue Assembly TOP Exit Vertical Including Offset Wall Thickness MINMAX TOP Exit Vertical & Horizontal FlueAdd 10 mm to the outlet end Assembling the ApplianceArrangement of Fuel BED AR02123 Lighting the Studio Thermostatic Remote ControlCommissioning CommissioningCheck Servicing / Fault Finding ChartsSymptom Cause Remedy Servicing RequirementsFlame Failure Functional Check Ignition Functional CheckDecorative Frame Replacing PartsWindow Frame Assembly GeneralVermiculite Panels MaIN Control AssemblyMaIN Burner Pilot Burner Bracket Pilot Unit AssemblyElectrode Thermocouple Ignition LeadGAS Valve Pilot InjectorPrimary Aeration Plate Magnetic safety valveControl BOX Main injectorFollow , Main Control Assembly Pressure and Leak Testing the ApplianceComponent Short Spares List Studio7TH Service 1ST Service3RD Service 5TH ServiceMember of the Stovax Group