INSTALLATION INSTRUCTIONS

SITE REQUIREMENTS

2.3 TOP FLUE VERTICAL KIT (8524/8524AN)

Vertical from the top of the appliance (See Diagram 4).

4

AR1673

A minimum vertical rise 3m (9’10") to a maximum 10m (32’10"). The basic kit comprises:

2 x 1m lengths

1 x 1m terminal length

1 x 52mm restrictor

1 x 47mm restrictor

1 x 60mm restrictor

Extra lengths may be added from the list below.

2.4TOP FLUE VERTICAL OFFSET KIT (8530/8530AN)

Used with kit 8524. A minimum rise of 500mm (191/2) is required to the first bend. See Diagram 1C.

2.5 EXTRA FLUE LENGTHS

All flue components are 150mm diameter (6")

NOMINAL

ACTUAL

STAINLESS

ANTHRACITE

LENGTH

LENGTH

FINISH

FINISH

200mm

140mm

8527

8527AN

500mm

440mm

8528

8528AN

1000mm

940mm

8529

8529AN

40° Bend

N/A

8507

8507AN

90° Bend

N/A

8508

8508AN

NOTE: Carefully consider:

a)Terminal positions

b)Flue supports

c)Weatherproofing

d)Fire precautions

For all the above options, you must conform to local and national codes of practice .

3. GAS SUPPLY

This appliance is intended for use on a gas installation with a governed meter.

3.1Before installation, ensure that the local distribution conditions (identification of the type of gas and pressure) and the adjustment of the appliance are compatible.

3.2Ensure the gas supply delivers the required amount of gas and is in accordance with the rules in force.

3.3You can use soft copper tubing on the installation and soft soldered joints outside the appliance and below the fire.

3.4A factory fitted isolation device is part of the inlet connection; no further isolation device is required.

3.5All supply gas pipes must be purged of any debris that may have entered prior to connection to the appliance.

3.6The gas supply enters through the silicone panel located on the bottom or rear of the outer box:

Slit with a sharp knife prior to passing the supply pipe through.

3.7The gas supply must be installed in a way that does not restrict the removal of the appliance for servicing and inspection.

4.VENTILATION

4.1This appliance requires no additional ventilation.

14

Image 14
Contents Studio Covering the Following Model Studio 22 Balanced flue 8704BFLEC P8704BFLECGAS CHECK FLUE CHECKFail Decreasing Temperature MAN ModeIncreasing Temperature GeneralLOW Battery Temp ModeTimer Mode Setting the TimeAll models Cleaning the StudioChanging the Studio Batteries Advice on Handling and Disposal of Fire Ceramics Arrangement of Fuel BEDHOT SURFACES Fire will not LightStudio 22 BF 8704BFLEC P8704BFLEC Technical SpecificationCovering the Following Models CATPacking Checklist Qty Description Fixing Kit containingBauhaus Frame Dimensions Size mm Steel Frame Dimensions Size mmProfil Frame Dimensions Size mm SITE REQUIREMENTS Flue and Chimney RequirementsTOP Exits Flue OptionsRear Exit TOP Flue UP & OUT KITExtra Flue Lengths TOP Flue Vertical KIT 8524/8524ANTOP Flue Vertical Offset KIT 8530/8530AN GAS SupplyAppliance Location Installation of the appliance InstallationSafety Precautions AR2117 Stud Work Installation Distance to Combustible MaterialFlue system see Installation, Flue Assembly SlipsApply a plaster finish to the chimney breast Studwork for Cool Wall Installation KIT Flue Assembly TOP Exit Vertical & Horizontal Flue Wall Thickness MINMAX TOP Exit Vertical Including OffsetAssembling the Appliance Add 10 mm to the outlet endArrangement of Fuel BED AR02123 Thermostatic Remote Control Lighting the StudioCommissioning CommissioningServicing Requirements Servicing / Fault Finding ChartsSymptom Cause Remedy CheckIgnition Functional Check Flame Failure Functional CheckGeneral Replacing PartsWindow Frame Assembly Decorative FrameMaIN Burner MaIN Control AssemblyVermiculite Panels Electrode Pilot Unit AssemblyPilot Burner Bracket Pilot Injector Ignition LeadGAS Valve ThermocoupleMain injector Magnetic safety valveControl BOX Primary Aeration PlatePressure and Leak Testing the Appliance Follow , Main Control AssemblyShort Spares List Studio Component5TH Service 1ST Service3RD Service 7TH ServiceMember of the Stovax Group