Heat & Glo LifeStyle XLR-PB-AU, XLR-N-AU manual Install the Ceiling Firestop, Pipe SLP

Page 32

C. Install the Ceiling Firestop

A ceiling firestop MUST be used between floors and attics.

SLP pipe only - Frame opening 9 in. x 9 in. (229 mm x 229 mm) whenever the vent penetrates a ceiling/floor (see Figure 8.3).

Frame the area with the same sized lumber as used in ceiling/floor joist.

The ceiling firestop may be installed above or below the ceiling joists when installed with a attic insulation shield. It must be under joists between floors that are not insulated. Refer to Figure 8.4.

Secure with three fasteners on each side.

WARNING! Risk of Fire! DO NOT pack insu- lation around the vent. Insulation must be kept back from the pipe to prevent overheating.

 

 

ATTIC ABOVE

 

 

A

 

 

A

 

PIPE

A

 

SLP

9 in. (229 mm)

Figure 8.3

Installing Ceiling Firestop

 

 

INSTALL ATTIC INSULATION SHIELDS

 

BEFORE OR AFTER INSTALLATION OF VENT SYSTEM

 

3 FASTENERS

 

 

PER SIDE

 

 

CEILING FIRESTOP

CEILING FIRESTOP

 

INSTALLED BELOW CEILING

INSTALLED ABOVE CEILING

 

Figure 8.4 Installing the Attic Shield

 

32

Heat & Glo • XLR-N-AU, XLR-PB-AU2198-906 Rev. M • 5/12

 

Image 32
Contents What to do if you smell gas Ref No GSCS20139 AS4558SAI Global Models XLR-N-AU, XLR-PB-AU Congratulations Homeowner Reference InformationTable of Contents User GuideAppliance Setup TroubleshootingComponent Access FinishingAustralian Warranty Information Limited Lifetime WarrantyOther Rights This warranty is void if PerthListing and Code Approvals Your Fireplace Gas Fireplace SafetyOperating Instructions User Guide Fixed Glass Assembly Remote Controls, Wall Controls and Wall SwitchesClear Space Decorative Doors and FrontsNine Hour Safety Shutdown Feature Control Module OperationAGE 110/120 VAC or 220/240 Lighting Instructions IPIFinal inspection by After Fireplace is Lit Frequently Asked QuestionsInitial Break-in Procedure Maintenance and Service Maintenance Tasks-HomeownerGlass Cleaning Decorative DoorsMaintenance Tasks-Qualified Service Technician Gasket Seal and Glass Assembly InspectionFirebox Control Compartment and Firebox TopGetting Started Typical Appliance SystemInspect Appliance and Components Design and Installation ConsiderationsTools and Supplies Needed Framing and Clearances Selecting Appliance LocationConstructing the Appliance Chase ClearancesMantel and Wall Projections Mantels Combustible/Non-CombustibleMantel Leg Combustible/Non-Combustible Front Side Finishing DetailTermination Locations Vent Termination Minimum ClearancesMIN. Clearance in. mm Vent Information and Diagrams Top Vent Horizontal Termination Venting with 1 elbow Minimum MaximumTop Vent Horizontal Termination Venting with 2 elbowsTop Vent Vertical Termination No Elbows V1 Max= 44 ft .4 m Exhaust restrictor InstructionsTop Vent Vertical Termination Venting with 2 elbows V1 Minimum Maximum V1 + V2 MinimumTop Vent Vertical Termination Venting with 3 elbows V1 Minimum H1 + H2 Maximum V1 + V2 MinimumTop Vent Vertical Termination Venting with 4 elbows Vent Clearances and Framing Pipe Clearances to CombustiblesWall Penetration Framing Combustible Wall PenetrationInstall the Ceiling Firestop Pipe SLPVaulted Ceiling Installation Install Attic Insulation ShieldFlat Ceiling Installation Appliance Preparation Top VentInstalling the Optional Heat-Zone-240V Kit Securing and Leveling the ApplianceInstalling Vent Pipe SLP Pipe Assemble Vent SectionsAssemble Slip Sections Secure The Vent SectionsInstall Decorative Ceiling Components Disassemble Vent SectionsInstall Metal Roof Flashing Assemble and Install Storm CollarHeat Shield Requirements for Horizontal Termination Install Vertical Termination CapInstall Decorative Wall Components Install Horizontal Termination Cap 17 Venting through the WallGas Information Gas ConnectionAccess Through the Valve Assembly Valve Pressure TapsWiring Requirements IntelliFire Plus Ignition System WiringOptional Accessories Requirements Optional Remote Control Receiver LocationElectrical Service and Repair Junction Cord Information Junction Cord InformationNon-Combustible Materials Specification FinishingFraming and Finishing Instructions Finishing InstructionsFinishing Details Sealing Joints Required Fireplace Opening HeightTOP View Unlimited Facing Material 11 Overlap Fit Method Tonic or Martini Decorative Front13 Inside Fit Method Tonic Decorative Front Only Dimensions of Tonic Decorative Front Decorative FrontsAppliance Setup Verify Performance of Appliance Air Shutter SettingMedia Options IntelliFire Plus Ignition System TroubleshootingSymptom Possible Cause Corrective Action Ues to spark, and main Frequently Asked Questions/Troubleshooting Symptom Possible Cause Corrective ActionComponent Access Access Through the Valve Assembly Gas Valve Replacement Pilot Assembly ReplacementAppliance Dimension Diagram Reference MaterialsMaintenance Tasks Inspect Maintenance TasksVent Components Diagrams 165 mm 152 mmSLP-45 45 Elbow 168 mm 10-1/4 SLP90- 90 Elbow15-1/2 394 mm Snorkel Support Box-BlackCeiling Firestop Wall Thimble-Black Adapter SLP-HRC-SS SLP-HRC-ZC-SS Horizontal Termination CAP Service Parts XLR-N-AU, XLR-PB-AU#14 Valve Assembly Service Parts List XLR-N-AU, XLR-PB-AUContact Information