Heat & Glo LifeStyle LUX60 owner manual Install the Ceiling Firestop

Page 32

C. Install the Ceiling Firestop

A ceiling firestop MUST be used between floors and at- tics.

Frame an opening 10 in. by 10 in. (254 mm by 254

mm)whenever the vent penetrates a ceiling/floor (see Figure 8.3).

Frame the area with the same sized lumber as used in ceiling/floor joist.

The ceiling firestop may be installed above or below the ceiling joists when installed with a attic insulation shield. It must be under joists between floors that are not insulated. Refer to Figure 8.4.

Secure with three fasteners on each side.

WARNING! Risk of Fire! DO NOT pack insulation around the vent. Insulation must be kept back from the pipe to pre- vent overheating.

Attic Above

10 in. (254 mm)

10 in. (254 mm)

Hole should measure

10 in. x 10 in.

(254 mm x 254 mm)

inside to inside

Figure 8.3 Installing Ceiling Firestop

Install attic insula- tion shields before or after installation

of vent system.

3 fasteners per side

 

 

 

 

 

 

 

Ceiling

 

firestop

Ceiling

 

firestop

 

 

installed below ceiling.

installed above ceiling.

Figure 8.4 Installing the Attic Shield

 

 

 

32

Heat & Glo • LUX60 • 4062-116 • Rev. G • 4/11

Image 32
Contents Installation and Operation ModelsCongratulations Homeowner Reference InformationTable of Contents Reference Materials  B. Limited Lifetime Warranty Limited Lifetime WarrantyWarranty Conditions Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Your Fireplace Gas Fireplace SafetyOperating Instructions Fixed Glass Assembly Clear SpaceDecorative Doors and Fronts Operation of the LUX60System Operation Before Lighting FireplaceMatching Security Codes For Your Safety Read Before Lighting IntelliFire Ignition System IPI Lighting InstructionsAfter Fireplace is Lit Frequently Asked QuestionsInitial Break-in Procedure Glass Cleaning Maintenance and ServiceMaintenance Tasks-Homeowner Venting Remote ControlDoors, Surrounds, Fronts Maintenance Tasks-Qualified Service Technician Gasket Seal and Glass Assembly InspectionFirebox Control Compartment and Firebox TopLight Glass Replacement/Cleaning LED Light Bar ReplacementClean Porcelain Panels BackRemove Screws Getting Started Typical Appliance SystemInspect Appliance and Components Design and Installation ConsiderationsTools and Supplies Needed Assemble Steel Stud Kit Framing and ClearancesSelect Appliance Location Construct the Appliance Chase ClearancesClearances to Combustibles Termination Locations Vent Termination Minimum ClearancesMinimum Clearances for Termination Vent Information and Diagrams Approved PipeVent Table Key Use of ElbowsOne Elbow Vent DiagramsTop Vent Horizontal Termination Two 45 Elbows replacing One 90 Elbow Three ElbowsTwo Elbows Top Vent Vertical TerminationNo Elbow Vent Clearances and Framing Pipe Clearances to CombustiblesWall Penetration Framing Combustible Wall PenetrationInstall the Ceiling Firestop Ceiling firestop Must be used between floors and at- ticsVaulted Ceiling Installation Install Attic Insulation ShieldFlat Ceiling Installation Appliance Preparation Secure and Level the ApplianceInstall Vent Pipe Attach Pipe to the Firebox AssemblyAssemble Vent Sections Assemble Pipe SectionsAssemble Slip Sections Secure the Vent SectionsInstall Metal Roof Flashing Disassemble Vent SectionsAssemble and Install Storm Collar 13 Assembling the Storm CollarInstall Vertical Termination Cap Heat Shield Requirements for Horizontal TerminationInstall Horizontal Termination Cap 16 Venting through the wallShrouds HHT ShroudsField Constructed Shrouds Open Top Shroud may be used with DVP-TV, DVP-TVHWMailbox Style Shroud may be used with DVP-TV, DVP-TVHW Roofed Style Shroud may be used with DVP-TV, DVP-TVHWGas Connection Gas InformationGas Pressure Install Flame Solenoid Setting Flame Height/Manifold PressureElectrical Information Wiring RequirementsElectrical Service and Repair Junction Box Installation Junction Box DetailWall Finishing Standard 1/2 in mm SheetrockAdditional Decorative Finishing up to 1 in mm Thick Additional Decorative Finishing over 1 in mm ThickAppliance Setup Remove Glass AssemblyAir Shutter Access & Adjustment Clean the ApplianceOutside Burner Tube Air Shutter Adjustment Center Burner Tube Air ShutterInstall Glass Rock Install Glass RockTroubleshooting IntelliFire IPI Ignition SystemIntelliFire IPI Ignition System Appliance Dimension Diagram Reference MaterialsVent Components Diagrams DVP45DVP-TRAPFL DVP-TVHW DVP-TRAP Optional Components Contact Information Do not Discard this Manual