G. Install Vertical Termination Cap

Attach the vertical termination cap by sliding the inner collar of the cap into the inner flue of the pipe section while placing the outer collar of the cap over the outer flue of the pipe section.

Secure the cap by driving three self-tapping screws (supplied) through the pilot holes in the outer collar of the cap into the outer flue of the pipe (see Figure 10.15).

Termination Cap

Brackets/

 

(1 of three)

 

 

 

Bolts

 

 

Storm

Collar

Screws

Caulk

Figure 10.15 Install Vertical Termination Cap

H. Heat Shield Requirements for Horizontal Termination

WARNING! Risk of Fire! To prevent overheating and fire, heat shields must extend through the entire wall thick- ness.

DO NOT remove the heat shields attached to the wall shield firestop and the horizontal termination cap.

Heat shields must overlap 1-1/2 in. (38 mm) mini- mum.

There are two sections of the heat shield. One section is factory-attached to the wall shield firestop. The other section is factory-attached to the cap. See Figure 10.16.

If the wall thickness does not allow the required 1-1/2 in. (38 mm) heat shield overlap when installed, an extended heat shield must be used.

If the wall thickness is less than 4 in./102 mm the heat shields on the cap and wall shield firestop must to be trimmed. A minimum 1-1/2 in. (38 mm) overlap MUST be maintained.

Use an extended heat shield if the finished wall thickness is greater than 7-1/4 in. (184 mm).

The extended heat shield may need to be cut to length maintaining sufficient length for a 1-1/2 in. (38 mm) overlap between heat shields.

Attach the extended heat shield to either of the existing heat shields using the screws supplied with the extended heat shield. Refer to “Vent Components Diagrams” in the back of this manual.

Rest the small leg on the extended heat shield on top of the pipe section to properly space it from the pipe section.

Important Notice: Heat shields may not be field constructed.

Heat & Glo • LUX60 • 4062-116 • Rev. G • 4/11

39

Image 39
Contents Models Installation and OperationHomeowner Reference Information CongratulationsTable of Contents Reference Materials Limited Lifetime Warranty  B. Limited Lifetime WarrantyWarranty Conditions Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Gas Fireplace Safety Operating InstructionsYour Fireplace Operation of the LUX60 Fixed Glass AssemblyClear Space Decorative Doors and FrontsBefore Lighting Fireplace Matching Security CodesSystem Operation IntelliFire Ignition System IPI Lighting Instructions For Your Safety Read Before LightingFrequently Asked Questions Initial Break-in ProcedureAfter Fireplace is Lit Maintenance and Service Maintenance Tasks-HomeownerGlass Cleaning Remote Control Doors, Surrounds, FrontsVenting Control Compartment and Firebox Top Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection FireboxLED Light Bar Replacement Light Glass Replacement/CleaningBack Clean Porcelain PanelsRemove Screws Typical Appliance System Getting StartedDesign and Installation Considerations Tools and Supplies NeededInspect Appliance and Components Framing and Clearances Select Appliance LocationAssemble Steel Stud Kit Clearances Construct the Appliance ChaseClearances to Combustibles Vent Termination Minimum Clearances Termination LocationsMinimum Clearances for Termination Use of Elbows Vent Information and DiagramsApproved Pipe Vent Table KeyVent Diagrams Top Vent Horizontal TerminationOne Elbow Three Elbows Two 45 Elbows replacing One 90 ElbowTop Vent Vertical Termination No ElbowTwo Elbows Combustible Wall Penetration Vent Clearances and FramingPipe Clearances to Combustibles Wall Penetration FramingCeiling firestop Must be used between floors and at- tics Install the Ceiling FirestopInstall Attic Insulation Shield Flat Ceiling InstallationVaulted Ceiling Installation Secure and Level the Appliance Appliance PreparationAssemble Pipe Sections Install Vent PipeAttach Pipe to the Firebox Assembly Assemble Vent SectionsSecure the Vent Sections Assemble Slip SectionsDisassemble Vent Sections Install Metal Roof Flashing13 Assembling the Storm Collar Assemble and Install Storm CollarHeat Shield Requirements for Horizontal Termination Install Vertical Termination Cap16 Venting through the wall Install Horizontal Termination CapOpen Top Shroud may be used with DVP-TV, DVP-TVHW ShroudsHHT Shrouds Field Constructed ShroudsRoofed Style Shroud may be used with DVP-TV, DVP-TVHW Mailbox Style Shroud may be used with DVP-TV, DVP-TVHWGas Information Gas PressureGas Connection Setting Flame Height/Manifold Pressure Install Flame SolenoidWiring Requirements Electrical Service and RepairElectrical Information Junction Box Detail Junction Box InstallationStandard 1/2 in mm Sheetrock Wall FinishingAdditional Decorative Finishing over 1 in mm Thick Additional Decorative Finishing up to 1 in mm ThickClean the Appliance Appliance SetupRemove Glass Assembly Air Shutter Access & AdjustmentCenter Burner Tube Air Shutter Outside Burner Tube Air Shutter AdjustmentInstall Glass Rock Install Glass RockIntelliFire IPI Ignition System TroubleshootingIntelliFire IPI Ignition System Reference Materials Appliance Dimension DiagramDVP45 Vent Components DiagramsDVP-TRAPFL DVP-TVHW DVP-TRAP Optional Components Do not Discard this Manual Contact Information