Vermont Casting DVRTSB manual Vertical Sidewall Installation, Maximum vent run with elbows

Page 15

The maximum number of 90° elbows per side wall installation is three (3).

If a 90° elbow is fitted directly on top of the fireplace flange, the maximum horizontal vent run before the termination or a vertical rise is 36” (914 mm).

 

Max. 36"

 

(914mm)

Max. 20"

(508mm)

 

FP1381

Fig. 20

Maximum horizontal vent run.

If a 90° elbow is used in the horizontal vent run (level height maintained) the maximum horizontal vent length is reduced by 36” (914 mm). (Fig. 21) This does not apply if the 90° elbows are used to increase or redirect a vertical rise. (Fig. 21)

Example: According to the chart the maximum horizon- tal vent length in a system with a 7.5’ vertical rise is 20’ (6 m) and if a 90° is required in the horizontal vent it must be reduced to 17’ (5.2 m).

Dimension A plus B must not be greater than 17’ (5.2m). (Fig. 21)

90°

AB

A + B = 17' Max.

(5.2m)

7'6"

(2286mm)

FP1382

Fig. 21 Maximum vent run with elbows.

The maximum number of 45° elbows permitted per side wall installation is two (2). These elbows can be installed in either the vertical or horizontal run.

For each 45° elbow installed in the horizontal run, the length of the horizontal run MUST be reduced by 18” (45cm). This does not apply if the 45° elbows are installed in the vertical part of the vent system.

The maximum number of elbow degrees in a system is 270°. (Fig. 22)

DVRTSB Bay Window Fireplace

Example: In Fig. 22

Elbow 1 = 90°

Elbow 2 = 45°

Elbow 3 = 45°

Elbow 4 = 90°

Total Angular Variation = 270°

 

1 + 2 + 3 + 4 = 270o

1

1

2

2

3

3

4

4

 

FP1383

Fig. 22

Maximum number of elbows allowed.

Vertical Sidewall Installation

STEP 1

Locate vent opening on the wall. It may be necessary to first position the fireplace and measure to obtain hole location. Depending on whether the wall is combustible or noncombustible, cut opening to size. (Fig. 23) For combustible walls first frame in opening. (Fig. 23)

Combustible Walls: Cut a 9³⁄”H x 9³⁄”W (240 x 240mm) hole through the exterior wall and frame as shown in Figure 23.

Noncombustible Walls (Fig. 23): Hole opening must be 7¹⁄” (190 mm) in diameter.

Vent Opening for Combustible Wall

9³⁄

(240 mm)

9³⁄

(240 mm)

Framing Detail

Opening for Noncombustible Wall

7¹⁄

(190 mm)

VO584-100

Fig. 23 Locate vent opening on wall.

10003848

15

Image 15
Contents Homeowner’s Installation Operating Manual Table of Contents National Fuel Gas Code Ansi Z223.1/NFPA Installation & Operating InstructionsFireplace Dimensions Installed as Top Vent Framing DimensionsDvrtsb Top Vent Dvrtsb Rear Vent Fireplace Dimensions Installed as Rear VentHearth Locating Your FireplaceClearance to Combustibles MantelsGas Inlet and Manifold Pressures Gas Line InstallationFinal Finishing Gas SpecificationsRemote ON/OFF Switch Installation Alternate Switch LocationEB-1 Electrical Box Remove flue cover and flue pipe Optional Top Vent ApplicationLocation of Vent Termination General Venting Information Termination LocationTermination location requirements Canadian Installations1 US Installations2Twist Lock Pipes General Information for Connecting Vent PipesCanadian Installations USA InstallationsExample a How to Use the Vent GraphRear Wall Vent Installation Rear Wall Vent ApplicationsZero clearance sleeve is only required for combustible walls Vertical Sidewall ApplicationsMaximum vent run with elbows Vertical Sidewall InstallationHorizontal length requirement Always install horizontal venting on a level planeVertical Through-the-Roof Applications Below Grade InstallationEnlarged ends of the vent section always face downward Vertical Through-The-Roof InstallationAttic Insulation Shield Upper Floor Twist Lock Venting Components Side Glass Frame Glass InformationLouvre Removal Glass/Frame RemovalClean the glass after the first two weeks of operation Glass CleaningCeramic Refractory Installation Installation of LogsRN/RP Models Flame Characteristics Flame & Temperature AdjustmentLava Rock & Ember Material Ceramic Ember Rocks Pt. #To Turn Off Gas To Heater Lighting and Operating InstructionsTroubleshooting the Gas Control System Honeywell Millivolt Valve SIT 820 Nova Gas Control Valve Fig Fuel Conversion InstructionsSIT top Convertible Pilot PSE PilotCleaning the Standing Pilot Control System Burner and Burner CompartmentBrass Trim OFF DescriptionDvrtsb Dvrtsb Bay Window Fireplace Fan Kits Wall mounted thermostat control Remote ControlsON/OFF and Temperature Model Function/s ControlledDvrtsb Bay Window Fireplace Limited Lifetime Warranty Efficiency Ratings