Regency P42-LP3, P42-NG3 Horizontal Installations, Below Grade Installation, Snorkel Terminations

Page 19

INSTALLATION

HORIZONTAL

INSTALLATIONS

1)Set the unit in its desired location. Check to determine if wall studs or roof rafters are in the way when the venting system is attached. If this is the case, you may want to adjust the location of the unit. Rough in the gas preferably on the right side of the unit and the electrical (junction block is on the left side) on the left.

2)Direct Vent pipe and fittings are designed with special twist-lock connections to con- nect the venting system to the appliance flue outlet. A twist-lock appliance adaptor is an available option that must be used in conjunction with the Simpson Dura-Vent Direct Vent GS system. Install the adaptor after the unit is set in its desired location otherwise the unit will not fit through the 36- 5/8" (930mm) high frame opening.

3)Put a bead of silicone inside the outer section of the adapter and a bead of Stove Mate on the inner collar. Slip the adapter over the existing inner and outer flue collar and fasten to the outer collar only with the 3 supplied screws (drilling pilot holes will make this easier). Level the fireplace and fasten it to the framing using nails or screws through the nailing strips.

4)Assemble the desired combination of pipe and elbows to the appliance adaptor and twist-lock for a solid connection.

Note:

a)Twist-lock procedure: Four indenta- tions, located on the female ends of pipes and fittings, are designed to slide straight onto the male ends of adjacent pipes and fittings, by orienting the four pipe indentations so they match and slide in to the four entry slots on the male ends. (Diagram 1) Push the pipe sections completely together, then twist-lock one section clockwise ap- proximately one-quarter turn, until the two sections are fully locked. The fe- male locking lugs will not be visible from the outside, on the Black Pipe or fittings. They may be located by examining the inside of the female ends.

Diagram 1

Note: Apply sealant "Mill-Pac" to inner pipe and high temp silicone seal- ant to outer pipe on every twist- lock joint.

b)Horizontal runs of vent must be sup- ported every 3 feet (0.9meter). Wall straps are available for this purpose.

5)Mark the wall for a 10" x 10" (254mm x 254mm) square hole. The center of the square hole should line up with the center- line of the horizontal pipe. Cut and frame the 10 inch (254mm) square hole in the exterior wall where the vent will be terminated.

If the wall being penetrated is constructed of non-combustible material, i.e. masonry block or concrete, a 7" (178mm) diameter (7-1/2" (190mm) for flex) hole is accepta- ble.

Diagram 2

Note:

a)The horizontal run of vent must be level, or have a 1/4 inch rise for every 1 foot of run towards the termination. Never allow the vent to run downward. This could cause high temperatures and may present the possibility of a fire.

b)The location of the horizontal vent ter- mination on an exterior wall must meet all local and national building codes, and must not be blocked or obstructed. For External Vent Terminal Locations, see diagram on page 9.

c)Snorkel Terminations:

For installations requiring a vertical rise on the exterior of the building, 14-inch and 36-inch tall Snorkel Terminations (diagram 3 & 4) are available, as well as the standard Riser Vent, diagram 3a. Follow the same installation procedures as used for standard Horizontal Termi- nation. NEVER install the snorkel upside down.

NOTE: For Snorkel terminations in ABOVE grade installations, follow nation- al or local code requirements.

*Diagrams 3, 3a & 4: As specified in CGA B149 Installation Code. Local codes or regulations may require different clearances.

Diagram 3

Note: Riser Vent is only for use in above grade termina- tions.

Diagram 3a

Below Grade Installation

If the Snorkel Termination must be installed below grade, i.e. basement application, prop- er drainage must be provided to prevent water from entering the Snorkel Termination. Refer to Diagram 4.

Do not attempt to en- close the Snorkel within the wall, or

any other type of en-

closure.

Diagram 4

Regency P42-3 Zero Clearance Direct Vent Gas Fireplace

19

Image 19
Contents P42 Gas Fireplace To the New Owner Information for MOBILE/MANUFACTURED Homes After First SaleTable of Contents Copy of Safety Decal for P42 Safety LabelSave These Instructions InstallationGeneral Safety Information Installation ChecklistOptional Heat Release Unit Specifications Locating Your GAS StoveManufactured Mobile Home Additional Requirements Optional Duct SystemMantel LEG Clearances Clearances MantelsVent Restrictor TOP Assembly Nailing StripsFraming Finishing Venting IntroductionExterior Vent Termination Regency Direct Vent System Flex Horizontal Terminations Only Venting4DT-AJB Rigid Pipe Venting Components ListTermination Rigid Pipe VentingAlternate HorizontalVent guard may be required, check local codes Rigid Pipe Venting Arrangements Horizontal TerminationsFor All Horizontal Terminations Propane & Natural Gas Rigid Pipe Venting Arrangements Vertical Terminations Vent restrictor #6 must be used Alternate Approved Caps Vertical Termination With CO-LINEAR Flex SystemRequired Parts DescriptionInstallation Below Grade Installation Horizontal InstallationsSnorkel Terminations Continue to assemble pipe lengths Vertical TerminationOffset Chart Installation ProceduresFor Regency Direct Vent System Flex GAS Pipe Pressure Testing GAS Line InstallationHigh Elevation Aeration Brick Panels Adjustment Burner tray without front logs in place LOG SET InstallationNatural GAS PropaneNot under the gas line Standard Flush DoorFlush Louvers Double Screen DoorBAY Louvers Optional BAY DoorOptional Bay Trim Full Screen Front Full Screen Door Frame InstallationHinge Location Bottom Grill Hinge Screen Door To Thermocouple T Valve Wiring DiagramDo not cut the ground terminal off under any circumstances Operating Instructions Remote ControlOptional Wall Switch Lighting ProcedureClean. See installation Temperatures keep children, clothingCopy of the Lighting Plate Instructions First Fire MaintenanceMaintenance Shutdown ProcedureThermopile Thermocouple Glass ReplacementLOG Replacement GOLD-PLATED LouversRemoving the FAN Replacing the FAN Shut the power offInstalling Valve P42 Main Assembly Parts ListP42 Burner & LOG Assembly P42 Flush Door & Louvers P42 BAY Front & Louvers Regency P42-3 Zero Clearance Direct Vent Gas Fireplace Regency P42-3 Zero Clearance Direct Vent Gas Fireplace Conditions WarrantyInstaller Please complete the following information