Regency P42-NG3, P42-LP3 Vertical Termination, Continue to assemble pipe lengths

Page 20
Diagram 1

INSTALLATION

6)The arrow on the vent cap should be pointing up. Insure that the 1-1/4"(32mm) clearances to combustible materials are maintained (Diagram 5). Install the termina- tion cap.

Note: If installing termination on a siding covered wall, a vinyl siding stand- off or furring strips must be used to ensure that the termination is not recessed into the siding.

9)Install wall thimble in the center of the 10" (254mm) square and attach with wood screws (Diagram 6).

Diagram 7

Diagram 3

Diagram 5

The four wood screws provided should be replaced with appropriate fasteners for stucco, brick, concrete, or other types of sidings.

7)Before connecting the horizontal run of vent pipe to the vent termination, slide the Wall Thimble (Part # 942) over the vent pipe.

8)Slide the appliance and vent assembly to- wards the wall carefully inserting the vent pipe into the vent cap assembly. It is impor- tant that the vent pipe extends into the vent cap sufficient distance so as to result in a minimum pipe overlap of 1-1/4 inches (32mm). Secure the connection between the vent pipe and the vent cap by attaching the two sheet metal strips extending from the vent cap assembly into the outer wall of the vent pipe. Use the two sheet metal screws provided to connect the strips to the pipe section. See Diagram 6.

Diagram 6

VERTICAL

TERMINATION

1)Maintain the 1-1/4"(32mm) clear- ances (air spaces) to com-

bustibles when passing through ceilings, walls, roofs, enclosures, attic rafter, or oth- er nearby combustible surfac- es. Do not pack air spaces with insulation. Check pages 13-18 for the maximum verti- cal rise of the venting system and the maximum horizontal offset limitations.

2)Set the gas appliance in its desired location. Drop a plumb bob down from the

ceiling to the position of the appliance flue

exit, and mark the loca- tion where the vent will

penetrate the ceiling. Drill a small hole at his point.

Next, drop a plumb bob from

the roof to the hole previously drilled in the ceiling, and mark the spot where the vent will penetrate the roof. Determine if ceiling joists, roof rafters or other fram-

ing will obstruct the venting sys- tem. You may wish

to relocate the ap- pliance or to off- set, as shown in Diagram 2 to avoid cutting load bear- ing members.

Diagram 2

3)A Firestop spacer must be installed in the floor or ceiling of every level. To install the Firestop spacer in a flat ceiling or wall, cut a 10 inch (254mm) square hole. Frame the hole as shown in Diagram 3 and install the firestop.

4)Assemble the desired lengths of pipe and elbows. Ensure that all pipes and elbow connections are in the fully twist-locked position and sealed.

Note:

Apply sealant "Mill-Pac" to in- ner pipe and high temp sili- cone sealant to outer pipe on

every twist- lock joint.

5)Cut a hole in the roof centered on the small drilled hole placed in the roof in Step 2. The hole should be of sufficient size to meet the minimum requirements for clearance to combustibles of 1-1/4"(32mm). Slip the flashing under the shingles (shingles should overlap half the flashing) as per Diagram 4.

Diagram 4: The upper half of the flashing is installed under the roofing material and not nailed down until the chimney is installed.

This allows for small adjustments.

6)Continue to assemble pipe lengths.

Note: If an offset is necessary in the attic to avoid obstructions, it is impor- tant to support the vent pipe every 3 feet (0.9 meter), to avoid exces- sive stress on the elbows, and possible separation. Wall straps are available for this purpose (Diagram 2).

Galvanized pipe is desirable above the roof- line due to its higher corrosion resistance. Continue to add pipe sections through the flashing until the height of the vent cap meets the minimum height requirements specified in Diagram 5 or local codes. Note that for steep roof pitches, the vertical height must be in- creased.

20

Regency P42-3 Zero Clearance Direct Vent Gas Fireplace

Image 20
Contents P42 Gas Fireplace Information for MOBILE/MANUFACTURED Homes After First Sale To the New OwnerTable of Contents Safety Label Copy of Safety Decal for P42Installation General Safety InformationInstallation Checklist Save These InstructionsUnit Specifications Locating Your GAS Stove Manufactured Mobile Home Additional RequirementsOptional Duct System Optional Heat ReleaseClearances Mantels Mantel LEG ClearancesTOP Assembly Nailing Strips Framing FinishingVenting Introduction Vent RestrictorExterior Vent Termination Venting Regency Direct Vent System Flex Horizontal Terminations OnlyRigid Pipe Venting Components List 4DT-AJBRigid Pipe Venting AlternateHorizontal TerminationRigid Pipe Venting Arrangements Horizontal Terminations Vent guard may be required, check local codesFor All Horizontal Terminations Rigid Pipe Venting Arrangements Vertical Terminations Propane & Natural GasVent restrictor #6 must be used Vertical Termination With CO-LINEAR Flex System Required PartsDescription Alternate Approved CapsInstallation Snorkel Terminations Horizontal InstallationsBelow Grade Installation Vertical Termination Continue to assemble pipe lengthsFor Regency Direct Vent System Flex Installation ProceduresOffset Chart High Elevation GAS Line InstallationGAS Pipe Pressure Testing Aeration Brick Panels Adjustment LOG SET Installation Natural GASPropane Burner tray without front logs in placeStandard Flush Door Flush LouversDouble Screen Door Not under the gas lineOptional Bay Trim Optional BAY DoorBAY Louvers Full Screen Door Frame Installation Full Screen FrontHinge Location Bottom Grill Hinge Screen Door Do not cut the ground terminal off under any circumstances Wiring DiagramTo Thermocouple T Valve Remote Control Optional Wall SwitchLighting Procedure Operating InstructionsCopy of the Lighting Plate Instructions Temperatures keep children, clothingClean. See installation Maintenance MaintenanceShutdown Procedure First FireGlass Replacement LOG ReplacementGOLD-PLATED Louvers Thermopile ThermocoupleShut the power off Removing the FAN Replacing the FANInstalling Valve Parts List P42 Main AssemblyP42 Burner & LOG Assembly P42 Flush Door & Louvers P42 BAY Front & Louvers Regency P42-3 Zero Clearance Direct Vent Gas Fireplace Regency P42-3 Zero Clearance Direct Vent Gas Fireplace Warranty ConditionsInstaller Please complete the following information