Lochinvar 5 operation manual Install vent and combustion air piping, Air intake/vent connections

Page 15

Installation & Operation Manual

2 General venting (continued)

Install vent and combustion air piping

￿DANGER The SYNC boiler must be vented and supplied with combustion and ventilation

air as described in this section. Ensure the vent and air piping and the combustion air supply comply with these instructions regarding vent system, air system, and combustion air quality. See also Section 1 of this manual.

Inspect finished vent and air piping thoroughly to ensure all are airtight and comply with the instructions provided and with all requirements of applicable codes.

Failure to provide a properly installed vent and air system will cause severe personal injury or death.

The SYNC boiler vent and air piping can be installed through the roof or through a sidewall. Follow the procedures in this manual for the method chosen. Refer to the information in this manual to determine acceptable vent and air piping length.

You may use any of the vent/air piping methods covered in this manual. Do not attempt to install the SYNC boiler using any other means.

You must also install air piping from outside to the boiler air intake adapter unless following the Optional Room Air instructions on page 18 of this manual. The resultant installation is direct vent (sealed combustion).

Air intake/vent connections

1. Combustion Air Intake Connector (FIG. 2-4) - Used to

￿WARNING

￿WARNING

NOTICE

This appliance requires a special venting system. Use only approved stainless steel, PVC, CPVC or polypropylene pipe and fittings listed in Tables 2C, 2D, and 2F for vent pipe, and fittings. Failure to comply could result in severe personal injury, death, or substantial property damage.

DO NOT mix components from different systems. The vent system could fail, causing leakage of flue products into the living space. Mixing of venting materials will void the warranty and certification of the appliance.

Installation must comply with local requirements and with the National Fuel Gas Code, ANSI Z223.1 for U.S. installations or CSA B149.1 for Canadian installations.

provide combustion air directly to the unit from outdoors. A

fitting is provided on the unit for final connection.

Combustion air piping must be supported per guidelines

listed in the National Mechanical Code, Section 305, Table

305.4 or as local codes dictate.

2. Vent Connector (FIG.'s 2-5 thru 2-8) - Used to provide a

passageway for conveying combustion gases to the

outside. A transition fitting is provided on the unit for

final connection. Vent piping must be supported per the

National Building Code, Section 305, Table 305.4 or as

local codes dictate.

Figure 2-4Near Boiler Air Piping

AIR

￿WARNING

￿CAUTION NOTICE

For closet and alcove installations, CPVC, polypropylene or stainless steel material MUST BE used in a closet/alcove structure. Failure to follow this warning could result in fire, personal injury, or death.

Improper installation of venting systems may result in injury or death.

Follow the instructions in Section 1, page 11 of this manual when removing a boiler from an existing vent system.

￿WARNING Do not connect any other appliance to the vent pipe or multiple boilers to a

common vent pipe. Failure to comply could result in severe personal injury, death, or substantial property damage.

15

Image 15
Contents Save this manual for future reference Contents Please read before proceeding When servicing boilerBlowers Sync How it worksModels 1.0 1.3 Sync RatingsBefore locating the boiler, check Installation must comply withCloset and alcove installations Determine boiler location1Closet Installation Minimum Required Clearances Provide air openings to room Prevent combustion air contaminationFlooring and foundation When using an existing vent system to install a new boiler Products to avoidAreas likely to have contaminants Remove boiler from wood pallet When removing a boiler from existing common vent system5Combustion Air Through Ducts Minimum Recommended Combustion AIR Supply to Equipment Room General venting Direct venting options Sidewall VentDirect venting options Vertical Vent Air intake/vent connections Install vent and combustion air pipingSizing Requirements for installation in CanadaAir inlet pipe materials MaterialsOptional room air Primer Material StandardVent pipe Vent fittingsCentrotherm InnoFlue SW Duravent Polypro PolypropyleneSupplied with the vent system Stainless steel ventSidewall direct venting Vent/air termination sidewallDetermine location 2B Alternate Clearance to Gravity Air Inlets Found in this manual Prepare wall penetrationsMultiple vent/air terminations Prepare wall penetrations Alternate Field Supplied OptionsVertical direct venting Vent/air termination verticalPrepare roof penetrations 3Vertical Terminations with Multiple Boilers Hydronic piping Circulator sizing Near boiler piping connectionsExample Hot Water Generator pump sizingNear boiler piping components 5Single Boiler Primary/Secondary Piping Model Number of Units Manifold Pipe Sizes in Inches mm Gas connections Connecting gas supply pipingPropane Gas Natural gasCheck inlet gas supply GAS Piping Size ChartGas Pressure Gas valve replacementField wiring Installation must comply withLine voltage connections Flow switch field supplied EnableOutdoor temperature sensor Louver proving switchRuntime contacts System supply sensor Wiring of the cascadeAlarm contacts Boiler management system3Low Voltage Field Wiring Connections Condensate drain Condensate disposalFill and test water system Freeze protection when usedStart-up Check/control water chemistryInspect/check condensate lines and fittings Check for gas leaksCheck thermostat circuits Inspect/fill condensate systemCheck system and boiler Final checks before starting the boilerStart the boiler If boiler does not start correctlyFor Your Safety Read Before Operating Natural Gas Propane Set space heating operationSet Hot Water Generator HW operation Configuration of the cascadeGeneral Operating informationProtection features Boiler temperature regulation Outdoor reset operation, if usedCascade Sequence of the cascade HW operation with cascadeNight Setback operation with cascade Sequence of operation 1Status Screen Sync control moduleOperating information 2Main Menu Screen See the Sync User’s Information Manual for Instructions Maintenance Maintenance and annual startupService technician Owner maintenanceMaintenance Check boiler relief valve Flue vent system and air pipingCheck water system Check expansion tankCheck flame signal Check ignition ground wiringCheck all boiler wiring Check control settingsModel Kit Part Component Number Description Cleaning boiler heat exchangerNiosh stated First Aid Handling ceramic fiber materialsLOW Voltage 120 VAC High Voltage Diagrams2Ladder DiagramPart 3Wiring Diagram Page
Related manuals
Manual 12 pages 30.87 Kb

5 specifications

Lochinvar 5 is a cutting-edge residential boiler designed to meet the heating needs of modern homes while ensuring high efficiency and user convenience. As one of the latest offerings from Lochinvar, a trusted name in the heating industry, the Lochinvar 5 combines advanced technology with robust features that make it a top choice for homeowners and contractors alike.

One of the standout characteristics of the Lochinvar 5 is its impressive energy efficiency. It boasts an AFUE (Annual Fuel Utilization Efficiency) rating of up to 95%, which significantly reduces fuel consumption compared to traditional heating systems. This not only translates to lower energy bills for homeowners but also minimizes the environmental impact, aligning with the growing demand for sustainable energy solutions.

The Lochinvar 5 employs a highly efficient modulating burner technology that optimizes fuel usage based on real-time heating demand. This ensures that the boiler operates at peak efficiency, providing consistent warmth without unnecessary energy waste. The inclusion of advanced controls further enhances its performance, allowing users to adjust settings easily and monitor usage through a user-friendly digital display.

Durability and reliability are also paramount in the design of the Lochinvar 5. Constructed with high-quality materials, this boiler is built to withstand the rigors of daily use and provide long-lasting performance. Its compact design allows for flexible installation options, making it suitable for various residential settings, even where space is limited.

In addition to its impressive performance metrics, Lochinvar 5 is equipped with smart technology features that cater to the needs of modern consumers. Wi-Fi connectivity enables remote monitoring and control via a mobile app, giving homeowners the ability to adjust settings on the go. This feature not only enhances user convenience but also allows for proactive maintenance and alerts, helping to prevent potential issues before they arise.

Safety is a key consideration in the design of Lochinvar 5. It includes multiple safety features, such as a sealed combustion system that minimizes the risk of carbon monoxide leaks and an advanced monitoring system that ensures optimal operating conditions at all times.

In conclusion, the Lochinvar 5 stands out as an exceptional choice for those seeking a reliable, efficient, and smart residential heating solution. Its combination of advanced technologies, user-friendly features, and robust construction make it a leading option in the boiler market, ready to meet the demands of today’s homeowners. With an eye on energy efficiency and ease of use, Lochinvar 5 is well-equipped to provide comfortable, cost-effective heating for years to come.