1 Determine boiler location (continued)

Provide air openings to room:

Vent and air piping

The SYNC alone in boiler room

1.No air ventilation openings into the boiler room are needed when clearances around the SYNC are at least equal to the SERVICE clearances shown in FIG.’s 1-1 and 1-2. For spaces that do NOT supply this clearance, provide two openings as shown in FIG. 1-1. Each opening must provide one square inch free area per 1,000 Btu/hr of boiler input.

2.Combustion air openings are required when using the Room Air Option on page 18 of this manual.

The SYNC in same space with other gas or oil-fired appliances

1.Follow the National Fuel Gas Code (U.S.) or CSA B149.1 (Canada) to size/verify size of the combustion/ventilation air openings into the space.

The SYNC requires a special vent system, designed for pressurized venting.

The boiler is to be used for either direct vent installation or for installation using indoor combustion air. When room air is considered, see Section 4, Vertical Direct Venting. Note prevention of combustion air contamination below when considering vent/air termination.

Vent and air must terminate near one another and may be vented vertically through the roof or out a side wall, unless otherwise specified. You may use any of the vent/air piping methods covered in this manual. Do not attempt to install the SYNC using any other means.

Be sure to locate the boiler such that the vent and air piping can be routed through the building and properly terminated. The vent/air piping lengths, routing and termination method must all comply with the methods and limits given in this manual.

￿WARNING

The space must be provided with combustion/ventilation air openings correctly sized for all other appliances located in the same space as the SYNC.

Do not install the boiler in an attic.

Failure to comply with the above warnings could result in severe personal injury,

Prevent combustion air contamination

Install air inlet piping for the SYNC as described in this manual. Do not terminate vent/air in locations that can allow contamination of combustion air. Refer to Table 1A, page 10 for products and areas which may cause contaminated combustion air.

death, or substantial property damage.

￿WARNING

Ensure that the combustion air will not

2.Size openings only on the basis of the other appliances in the space. No additional air opening free area is needed for the SYNC because it takes its combustion air from outside (direct vent installation).

Flooring and foundation

Flooring

The SYNC is approved for installation on combustible flooring, but must never be installed on carpeting.

￿WARNING Do not install the boiler on carpeting even if foundation is used. Fire can result,

causing severe personal injury, death, or substantial property damage.

If flooding is possible, elevate the boiler sufficiently to prevent water from reaching the boiler.

contain any of the contaminants in Table 1A, page 10. Contaminated combustion air will damage the boiler, resulting in possible severe personal injury, death or substantial property damage. Do not pipe combustion air near a swimming pool, for example. Also, avoid areas subject to exhaust fumes from laundry facilities. These areas will always contain contaminants.

9

Image 9
Contents Save this manual for future reference Contents Please read before proceeding When servicing boilerBlowers Sync How it worksModels 1.0 1.3 Sync RatingsCloset and alcove installations Installation must comply withDetermine boiler location Before locating the boiler, check1Closet Installation Minimum Required Clearances Provide air openings to room Prevent combustion air contaminationFlooring and foundation When using an existing vent system to install a new boiler Products to avoidAreas likely to have contaminants Remove boiler from wood pallet When removing a boiler from existing common vent system5Combustion Air Through Ducts Minimum Recommended Combustion AIR Supply to Equipment Room General venting Direct venting options Sidewall VentDirect venting options Vertical Vent Air intake/vent connections Install vent and combustion air pipingSizing Requirements for installation in CanadaAir inlet pipe materials MaterialsOptional room air Vent pipe Material StandardVent fittings PrimerCentrotherm InnoFlue SW Duravent Polypro PolypropyleneSupplied with the vent system Stainless steel ventSidewall direct venting Vent/air termination sidewallDetermine location 2B Alternate Clearance to Gravity Air Inlets Found in this manual Prepare wall penetrationsMultiple vent/air terminations Prepare wall penetrations Alternate Field Supplied OptionsVertical direct venting Vent/air termination verticalPrepare roof penetrations 3Vertical Terminations with Multiple Boilers Hydronic piping Circulator sizing Near boiler piping connectionsExample Hot Water Generator pump sizingNear boiler piping components 5Single Boiler Primary/Secondary Piping Model Number of Units Manifold Pipe Sizes in Inches mm Gas connections Connecting gas supply pipingPropane Gas Natural gasCheck inlet gas supply GAS Piping Size ChartGas Pressure Gas valve replacementField wiring Installation must comply withLine voltage connections Outdoor temperature sensor EnableLouver proving switch Flow switch field suppliedAlarm contacts System supply sensor Wiring of the cascadeBoiler management system Runtime contacts3Low Voltage Field Wiring Connections Condensate drain Condensate disposalStart-up Freeze protection when usedCheck/control water chemistry Fill and test water systemCheck thermostat circuits Check for gas leaksInspect/fill condensate system Inspect/check condensate lines and fittingsStart the boiler Final checks before starting the boilerIf boiler does not start correctly Check system and boilerFor Your Safety Read Before Operating Natural Gas Propane Set space heating operationSet Hot Water Generator HW operation Configuration of the cascadeGeneral Operating informationProtection features Boiler temperature regulation Outdoor reset operation, if usedCascade Sequence of the cascade HW operation with cascadeNight Setback operation with cascade Sequence of operation 1Status Screen Sync control moduleOperating information 2Main Menu Screen Service technician Maintenance Maintenance and annual startupOwner maintenance See the Sync User’s Information Manual for InstructionsMaintenance Check water system Flue vent system and air pipingCheck expansion tank Check boiler relief valveCheck all boiler wiring Check ignition ground wiringCheck control settings Check flame signalModel Kit Part Component Number Description Cleaning boiler heat exchangerNiosh stated First Aid Handling ceramic fiber materialsLOW Voltage 120 VAC High Voltage Diagrams2Ladder DiagramPart 3Wiring Diagram Page
Related manuals
Manual 12 pages 30.87 Kb

5 specifications

Lochinvar 5 is a cutting-edge residential boiler designed to meet the heating needs of modern homes while ensuring high efficiency and user convenience. As one of the latest offerings from Lochinvar, a trusted name in the heating industry, the Lochinvar 5 combines advanced technology with robust features that make it a top choice for homeowners and contractors alike.

One of the standout characteristics of the Lochinvar 5 is its impressive energy efficiency. It boasts an AFUE (Annual Fuel Utilization Efficiency) rating of up to 95%, which significantly reduces fuel consumption compared to traditional heating systems. This not only translates to lower energy bills for homeowners but also minimizes the environmental impact, aligning with the growing demand for sustainable energy solutions.

The Lochinvar 5 employs a highly efficient modulating burner technology that optimizes fuel usage based on real-time heating demand. This ensures that the boiler operates at peak efficiency, providing consistent warmth without unnecessary energy waste. The inclusion of advanced controls further enhances its performance, allowing users to adjust settings easily and monitor usage through a user-friendly digital display.

Durability and reliability are also paramount in the design of the Lochinvar 5. Constructed with high-quality materials, this boiler is built to withstand the rigors of daily use and provide long-lasting performance. Its compact design allows for flexible installation options, making it suitable for various residential settings, even where space is limited.

In addition to its impressive performance metrics, Lochinvar 5 is equipped with smart technology features that cater to the needs of modern consumers. Wi-Fi connectivity enables remote monitoring and control via a mobile app, giving homeowners the ability to adjust settings on the go. This feature not only enhances user convenience but also allows for proactive maintenance and alerts, helping to prevent potential issues before they arise.

Safety is a key consideration in the design of Lochinvar 5. It includes multiple safety features, such as a sealed combustion system that minimizes the risk of carbon monoxide leaks and an advanced monitoring system that ensures optimal operating conditions at all times.

In conclusion, the Lochinvar 5 stands out as an exceptional choice for those seeking a reliable, efficient, and smart residential heating solution. Its combination of advanced technologies, user-friendly features, and robust construction make it a leading option in the boiler market, ready to meet the demands of today’s homeowners. With an eye on energy efficiency and ease of use, Lochinvar 5 is well-equipped to provide comfortable, cost-effective heating for years to come.