5. Connect Gas Piping

Size gas piping according to Appendix C – Gas Piping

SHUT OFF GAS SUPPLY before servicing the boiler.

ALL GAS PIPING MUST BE GAS TIGHT. Use gas rated thread compound

on all threaded joints to avoid leaks, which may result in fire or explosion.

SIZE GAS PIPING, regulators, valves, and meters so as to provide an adequate

gas flow and pressure to the boiler during operation. Failure to do so may cause poor combustion, noise, injury, or death.

1.Remove boiler door, locate gas valve and remove plastic shipping plug.

2.Thread a ¾" x 1½" nipple, a 90° street elbow, or a Honeywell flange onto the gas valve and pipe through the slot in the left jacket panel (Figure 5-a). In Canada, close

nipples and street ells are not approved for use as gas piping.

3.Pipe through the left jacket panel, and complete drip leg as shown (Figure 5-a).

5-a

6. Connect Boiler Water Piping

General system piping guidelines are included in Appendix D—System Piping.

Additionally, for this particular boiler install piping shown below (Figure 6-a).

 

RV

 

O

S

 

R

G

 

D

6-a

 

1.Apply sealant to all threads.

2.Screw the water supply manifold into the boiler outlet tapping “O.”

3.Orient the manifold with the relief valve on top.

4.Screw the relief valve into manifold tapping “RV”.

iThis installation is not complete until the relief valve is installed.

PIPE THE RELIEF VALVE DISCHARGE to a location where it will not harm

people or damage property. The relief valve may discharge scalding hot water or steam.

BLOCKING THE RELIEF VALVE may result in boiler explosion.

5.Screw the temperature-pressure gage into manifold tapping “G”.

6.Connect the system supply to the open end of the manifold "S" using a 1¼” male NPT fitting.

10

Image 10
Contents ES2 Page Whats in the crate? Specifications ES2 SeriesSpecifications Boiler Quick-Start InstallationAppendices Unpack the Crate Position the BoilerProvide Combustion Air Connect VentingES2 Vent Connector Horizontal Length Restrictions ft Connect VentingConnect Gas Piping Connect Boiler Water PipingConnect Boiler Water Piping Description Burnham Part NumberConnect Electrical Wiring Operating Mode Options Using IQ Boiler Control DisplayViewing the Operating Mode Options Status Code Displayed in STA ModeUsing the IQ Option Panel Changing the Adjustable ParametersMore Information about Adjustable Parameters Adjustment Mode OptionsUsing the Optional LCD Display Kit Check for Gas and Water LeaksPerform Startup Checks and Adjustments Boiler restartsAnnual Maintenance Checklist Troubleshooting IQ Boiler Control Status Codes when Err is not displayedTroubleshooting IQ Boiler Control Error Codes when Err is flashingIQ Option Panel Display Shows ERR Display Status Boiler / Control ActionsRepair Parts List Repair Parts List Burner Orifices LP Gas 1.20mm IQ Boiler Control Jacket Vestibule Panel Supply Water Manifold Internal Wiring Figure IW-1 Wiring DiagramInternal Wiring Figure IW-2 Wiring SchematicFigure IW-3 Single Zone System with Domestic Hot Water Tank Figure IW-5 Multiple Zone System with Zone Valves Figure IW-7 Multiple Zone System with Zone Valve Panel Appendix a Combustion Air Combined appliance Input BTU/hrAppendix B Venting Figure B-1 Typical Atmospheric Vent Installation This page Intentionally Left Blank Appendix C Gas Piping Length W.c. Pressure Drop FeetAppendix C Gas Piping Appendix D System PipingAppendix D System Piping Hot Water Boilers, Non-CondensingFigure D-0 Piping Schematic Symbols Figure D-W1 Water Boiler, Series Loop Figure D-W3 Water Boiler, Tankless Coil, Two or More Zones Figure D-W5 Water Boiler, Indirect Water Heater Appendix E Filling the System and Checking for Leaks Confirm that the boiler and system have no water leaksAppendix F Adjusting Gas Input Rate Natural Gas BoilersLeak Test Gas Piping Appendix F Adjusting Gas Input RateLP/Propane Gas Boilers Table F-1 Gas Flow Rate in Cu. Ft. / HrAppendix G Checking Draft and Combustion IQ Boiler Control Appendix H iq control systemIQ Control System Overview IQ Option PanelAppendix H IQ Control System IQ Display Kit EnviraCOM ThermostatsFactory Mounted Components Appendix H IQ Control System System Parts ListAdditional Information List Optional ComponentsService Record Limited Warranty