Burnham ES2 manual Appendix C Gas Piping, Appendix D System Piping

Page 37

APPENDIX C – Gas Piping (continued)

5.Bond all above-ground gas piping to a grounding electrode and ensure the piping is electrically continuous.

DO NOT USE GAS PIPING AS A GROUNDING ELECTRODE. Refer to

National Electrical Code, NFPA 70.

6.Install sediment trap, ground-joint union and manual shut-off valve upstream of boiler gas control valve and outside jacket.

7.When the piping is completed, test it for leaks.

(1)When testing over ½ psig, disconnect the boiler and its individual shut-off valve from the gas supply piping.

(2)When testing at ½ psig or less, isolate boiler from gas supply piping by closing boiler’s individual manual shut-off valve.

(3)Locate leaks using approved combustible gas detector or nonflammable, non-corrosive leak detection solution.

DO NOT CHECK FOR LEAKS USING OPEN FLAMES such as matches or

candles or devices that spark.

8.Repair any detected leaks.

APPENDIX D – System Piping

USE PROPER DESIGN AND INSTALLATION PRACTICES and observe all local codes when installing system piping. Property damage and injury may result from an improperly piped or

designed heating system.

i

Boiler damage caused by flawed system design or operation is excluded from our warranty.

 

Training and experience is required to design and install a piping system that will protect the boiler and provide many years of comfort to the building occupants. Be sure to protect the boiler from the following problems:

1.Corrosion

(1)Comply with the boiler’s specific water quality requirements. See the Specifications Section of this manual.

(2)Pressurize the system above the highest net positive suction head (NPSH) required for each circulator and ensure positive pressure at the uppermost point in the system.

(3)Maintain a closed boiler system using heat exchangers to transfer heat to open systems, such as domestic hot water systems.

(4)Purge the system completely of dissolved oxygen by bleeding all radiators and installing a properly installed air scoop or air vent.

(5)Repair leaking pipes, fittings, and vents to minimize the need to add makeup water.

(6)Do not fill the boiler with softened water unless makeup water is extremely hard and it is not possible to eliminate all system leaks. If filling the boiler with softened water, test regularly the water softener regularly to ensure that brine solution is not entering the boiler’s water supply.

2.Lime scale

(1)Repair leaking pipes, fittings, and vents to minimize the need to add makeup water.

37

Image 37
Contents ES2 Page Whats in the crate? ES2 Series SpecificationsSpecifications Boiler Quick-Start InstallationAppendices Position the Boiler Unpack the CrateConnect Venting Provide Combustion AirConnect Venting ES2 Vent Connector Horizontal Length Restrictions ftConnect Boiler Water Piping Connect Gas PipingDescription Burnham Part Number Connect Boiler Water Piping Connect Electrical WiringViewing the Operating Mode Options Using IQ Boiler Control DisplayOperating Mode Options Status Code Displayed in STA ModeMore Information about Adjustable Parameters Changing the Adjustable ParametersUsing the IQ Option Panel Adjustment Mode OptionsCheck for Gas and Water Leaks Using the Optional LCD Display KitBoiler restarts Perform Startup Checks and AdjustmentsAnnual Maintenance Checklist IQ Boiler Control Status Codes when Err is not displayed TroubleshootingIQ Boiler Control Error Codes when Err is flashing TroubleshootingDisplay Status Boiler / Control Actions IQ Option Panel Display Shows ERRRepair Parts List Repair Parts List Burner Orifices LP Gas 1.20mm IQ Boiler Control Jacket Vestibule Panel Supply Water Manifold Figure IW-1 Wiring Diagram Internal WiringFigure IW-2 Wiring Schematic Internal WiringFigure IW-3 Single Zone System with Domestic Hot Water Tank Figure IW-5 Multiple Zone System with Zone Valves Figure IW-7 Multiple Zone System with Zone Valve Panel Combined appliance Input BTU/hr Appendix a Combustion AirAppendix B Venting Figure B-1 Typical Atmospheric Vent Installation This page Intentionally Left Blank Length W.c. Pressure Drop Feet Appendix C Gas PipingAppendix D System Piping Appendix C Gas PipingHot Water Boilers, Non-Condensing Appendix D System PipingFigure D-0 Piping Schematic Symbols Figure D-W1 Water Boiler, Series Loop Figure D-W3 Water Boiler, Tankless Coil, Two or More Zones Figure D-W5 Water Boiler, Indirect Water Heater Confirm that the boiler and system have no water leaks Appendix E Filling the System and Checking for LeaksNatural Gas Boilers Appendix F Adjusting Gas Input RateLP/Propane Gas Boilers Appendix F Adjusting Gas Input RateLeak Test Gas Piping Table F-1 Gas Flow Rate in Cu. Ft. / HrAppendix G Checking Draft and Combustion IQ Control System Overview Appendix H iq control systemIQ Boiler Control IQ Option PanelAppendix H IQ Control System EnviraCOM Thermostats IQ Display KitAdditional Information List Appendix H IQ Control System System Parts ListFactory Mounted Components Optional ComponentsService Record Limited Warranty