10. Perform Startup Checks and Adjustments

FAILURE TO PERFORM THESE CHECKS of the boiler's combustion and

safety systems may result in serious property damage, injury, or death.

IF YOU SMELL GAS, STOP and repair the leak. Lighting the boiler when gas is

leaking may cause explosion or fire.

Follow the checklist below:

1.Verify that the venting, water piping, gas piping, and electrical systems are properly installed and checked.

2.Apply power to the boiler.

3.Adjust zone thermostat to maximum setting.

4.Allow gas line to purge of air.

q Boiler lights cleanly within 60 seconds.

5.Adjust gas input rate. See Appendix F

– Adjusting Gas Input Rate

10-a

qPilot and main burner flames appear clean and blue.

6.Disconnect pilot lead wires from gas valve (Figure 10-b).

qBoiler shuts off.

7.Reconnect pilot lead wires to gas valve.

qBoiler restarts.

10-b

8.Adjust zone thermostat to minimum setting. q Boiler shuts off.

9.Adjust zone thermostat to maximum setting.

10.Observe temperature gage as boiler heats.

11.Adjust the high limit setting to its minimum level (see "Programming High Limit" in Section 8).

q Boiler shuts off when temperature gage reads within 15°F of high limit setting.

12.Return high limit to the desired setting (see

"Programming High Limit" in Section 8).

13.Check draft. See Appendix G

– Checking Draft and Combustion.

qNo spillage observed.

14.Check combustion in the vent stack and record results in the spaces provided below.

_____

CO2

(less than 7%)

_____

O2

(more than 9%)

_____

CO

(less than 100 ppm, air free)

ANY FAILED STARTUP CHECK Must be corrected before placing the

boiler in service.

16

Image 16
Contents ES2 Page Whats in the crate? Specifications ES2 SeriesSpecifications Boiler Quick-Start InstallationAppendices Unpack the Crate Position the BoilerProvide Combustion Air Connect VentingES2 Vent Connector Horizontal Length Restrictions ft Connect VentingConnect Gas Piping Connect Boiler Water PipingConnect Boiler Water Piping Description Burnham Part NumberConnect Electrical Wiring Using IQ Boiler Control Display Viewing the Operating Mode OptionsOperating Mode Options Status Code Displayed in STA ModeChanging the Adjustable Parameters More Information about Adjustable ParametersUsing the IQ Option Panel Adjustment Mode OptionsUsing the Optional LCD Display Kit Check for Gas and Water LeaksPerform Startup Checks and Adjustments Boiler restartsAnnual Maintenance Checklist Troubleshooting IQ Boiler Control Status Codes when Err is not displayedTroubleshooting IQ Boiler Control Error Codes when Err is flashingIQ Option Panel Display Shows ERR Display Status Boiler / Control ActionsRepair Parts List Repair Parts List Burner Orifices LP Gas 1.20mm IQ Boiler Control Jacket Vestibule Panel Supply Water Manifold Internal Wiring Figure IW-1 Wiring DiagramInternal Wiring Figure IW-2 Wiring SchematicFigure IW-3 Single Zone System with Domestic Hot Water Tank Figure IW-5 Multiple Zone System with Zone Valves Figure IW-7 Multiple Zone System with Zone Valve Panel Appendix a Combustion Air Combined appliance Input BTU/hrAppendix B Venting Figure B-1 Typical Atmospheric Vent Installation This page Intentionally Left Blank Appendix C Gas Piping Length W.c. Pressure Drop FeetAppendix C Gas Piping Appendix D System PipingAppendix D System Piping Hot Water Boilers, Non-CondensingFigure D-0 Piping Schematic Symbols Figure D-W1 Water Boiler, Series Loop Figure D-W3 Water Boiler, Tankless Coil, Two or More Zones Figure D-W5 Water Boiler, Indirect Water Heater Appendix E Filling the System and Checking for Leaks Confirm that the boiler and system have no water leaksAppendix F Adjusting Gas Input Rate Natural Gas BoilersAppendix F Adjusting Gas Input Rate LP/Propane Gas BoilersLeak Test Gas Piping Table F-1 Gas Flow Rate in Cu. Ft. / HrAppendix G Checking Draft and Combustion Appendix H iq control system IQ Control System OverviewIQ Boiler Control IQ Option PanelAppendix H IQ Control System IQ Display Kit EnviraCOM ThermostatsAppendix H IQ Control System System Parts List Additional Information ListFactory Mounted Components Optional ComponentsService Record Limited Warranty