Crown Boiler 24-09, 24-11, 24-10, 24-08, 24-12, 24-06 Draw-Up Rods Alternating Pattern Manual Draw-up

Page 16

Figure 9: Draw-Up Rods (Alternating Pattern -

Manual Draw-up)

When you start, grind surfaces between adjoining sections should be approximately 3/8” apart. Use three (3) or four (4) passes at tightening the four (4) draw-up rods a little at a time so that sections are pulled up evenly. During the last pass, pay close attention to the silastic sealant as it squeezes when the sections come in close contact. The silastic sealant will continue to squeeze out wafer thin until the sections are connected metal to metal. While tightening the nuts, close attention should be given to the connection area to determine that the silastic has stopped squeezing out from between the sections. This will give assurance that the sections are assembled metal to metal. If the silastic has stopped squeezing out from the connection and the sections still do not appear to be drawn metal to metal, measure any gaps between the sections with a feeler gauge. A maximum gap of .025” is acceptable. Gaps should be measured at the outer edge of the connection. DO NOT PUNCTURE THE GASKET CREATED BY THE FIBERGLASS ROPE AND SILASTIC

SEALANT WITH THE FEELER GAUGE.

WARNING

Do not over torque draw up nuts after grind surfaces meet.

KEEP NIPPLES ALIGNED WITH NIPPLE PORTS. If necessary, tap edge of nipples lightly with a blunt tool or rod to keep nipples from cocking while sections are being drawn-up. DO NOT DRAW UP SECTION WHEN NIPPLES ARE COCKED. If the torque required becomes

excessive, periodically place a heavy block of wood over each nipple port and strike as squarely as possible with several blows to relieve tension on the draw-up rods.

n.CONTINUE ASSEMBLING SECTIONS IN THEIR RESPECTIVE ORDER alternating the draw-up rods from the upper to lower set of holes in draw-up lugs. Be certain that all sections are drawn up IRON-TO-IRON at all three (3) nipple ports.

BE SURE TO APPLY THE SEALANT to the groove in the ground joints between adjacent sections as the boiler operates with a positive pressure in the firebox and products of combustion will escape between sections unless the sections are properly sealed. The sealant should be applied before each section is placed on the assembly.

o.If a joint springs apart it must be redrawn tight within four (4) hours of the time of application of Silastic to that joint.

2.ASSEMBLY OF SECTIONS (HYDRAULIC DRAW- UP)

The entire boiler assembly may be drawn up at one time using hydraulic draw-up equipment providing the operation is completed within four (4) hours after application of the sealant.

a.Repeat steps 1a through 1k under “Field Assembled Sections (Manual Draw-Up).”

b.Continue driving sections in place (in their respective order) until all sections are in the assembly. Ground surfaces between adjoining sections should be spaced 1/4” to 3/8” apart. Spacing of more than 3/8” will limit number of sections that can be drawn up in one unit and could indicate cocked nipples.

WARNING

Sealant must be properly applied to ALL grooves. Failure to properly seal the boiler joints will result in combustion gas leaks through to joint. DO NOT operate boiler with combustion gas leaks. The sealant should be applied before each section is placed on the assembly.

On long boiler assemblies, it may be necessary to draw-up a partial block if the entire boiler is not ready to be drawn-up tight within four (4) hours of the first application of Silastic. If the block assembly time extends overnight, the partial block completed must be drawn-up tight before leaving the boiler overnight. If a joint springs out, it must be redrawn tight within four (4) hours of first application of Silastic to the joint.

c.Insert the three (3) ¾” draw-up rods (and couplings, if appropriate) through the tapped holes in the rear section extending them through the

16

Image 16
Contents Series Page Important Information Read Carefully Page Page Table of Contents Table of Contents Section I General Information Boiler RATINGS/DATA Section I General Information Locate the UnitBoiler Foundation Chimney or VentVents Faults & Suggestions Section II Cast Iron Block Assembly Assembly of Sections Manual DRAW- UPNipple Gauge Series 24 Section Arrangement Draw-Up Rods Alternating Pattern Manual Draw-up Center Section Channel Block Position Partial Block Draw-Up Hydraulic Draw-Up of Sections Section III Installation Instructions Canopy with Rear Flue Outlet Damper AssemblyBare Boiler Assembly Avoid Breathing Fiber Particulates and Dust Left Side Canopy Intermediate Bracket Mount Rear Observation Port Cover Refer to Figure Inspect ALL Boiler SealsSeries 24 Jacket Assembly Boiler Models 24-03 thru Burner Mounting Plate Refer to Figures 16 Mount Burner Adapter Plate to Burner Mounting PlatePurpose of Tappings Steam Boilers Steam Trim Steam Boilers Install Steam Trim This Is Intentionally Left Blank Purpose of Tappings Water Boilers Water Trim Burner Installation Water Boilers Install Water TrimBoiler Piping Heating Applications Page Parallel Piping Conversion Recommendation 1 Use when Recommendation 2 Use when Recommendation 3 Use when Page Page Page BMounting Elevations M&M 150, 64 Float Low Water Cut-offs Schematic Tankless Heater Piping 24-08 24-09 Return Temperature Control and Components CCW Open to SystemWater Boiler Pressure Relief Valve Hook-Up Typical Boiler Wiring with RTC Front Typical Boiler with RTC Return Sensor Rear Always Inspect Installation Before Section IV Operating InstructionsStarting Burner Fill Heating System with WaterFlame Failure Boil MIN Delay Test Controls Check Operation of High Limit ControlBoiler and System Cleaning Steam Boiler Boiler and System Cleaning Water Boilers Frequent Water Addition Oxygen CorrosionSection V Service Instructions Clean the Boiler FluewaysMaintenance of LOW Water Cutoff Devices General Maintenance Considerations OperationSection VI Burner Specifications OIL BurnersSection VII Repair Parts & Carton Contents Series 24 Master Parts List Section VII Repair Parts Jacket Carton Bare Boiler Assembly Section Joiner Carton Assy Rear Target Wall Carton Standard Steam Trim Carton Assy RTC Carton with Outdoor Reset Tankless Coil Components Boiler Water Section Viii Appendix Page Mechanical Page Mechanical Electrical Page Page Page Page Page Page Page Page Series 24 Boiler Circulator Selection Taco 20F Differential Boiler Recirculation Grundfos Circulating Pump Way Boiler Recirculation Bell and Gossett Circulating Pump Way Boiler Recirculation Armstrong Circulating Pump Way Appendix C Valve and Actuator Mounting Instructions ApplicationService Record PN 980417 S24 12/05