Baxi Potterton Gold FSB 30 HE manual Site Requirement, Sink, ± 10 from vertical, Min mm

Page 18

7.0 Site Requirement

Termination via internal discharge branch e.g sink waste - downstream

Direct Connect Fitting

Pipe must terminate

 

 

 

 

 

 

 

 

 

 

above water level but

 

 

 

 

 

 

 

 

 

 

below surrounding surface

 

Sink

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

10° 10°

Branch of Tee to be

± 10° from vertical

7.7

Condensate Disposal (cont.)

9. Ensure that the condensate can discharge freely (without

blockage or restriction of the pipe) into the drain.

10. Examples are shown of condensate pipe methods of

termination:-

 

 

i)

via an internal discharge branch

 

 

(e.g. sink waste) - Fig. C.

 

ii)

to an internal or external soil and vent pipe -

Fig. C

From Boiler

 

Fig. D.

iii)

to a drain or gully - Fig. E. Ensure that the

 

condensate can discharge freely (without

 

blockage or restriction of the pipe) into the

 

drain.

iv)

to a soakaway - Fig. F.

 

 

Termination to an internal soil and vent pipe

Direct Connect Fitting

From Boiler

Min. 450mm

Fig. D

Termination to a drain or gully

From Boiler

Fig. E

Pipe must terminate above water level but below surrounding surface

Termination to a purpose made soak-away

 

 

 

 

 

 

 

 

 

 

500mm Min

 

 

 

 

 

 

 

 

 

 

From Boiler

 

 

 

 

 

 

 

 

 

Holes in the soak-away must

 

 

 

 

 

 

 

 

 

 

face away from the building

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Fig. F

18© Baxi Heating UK Ltd 2011

Image 18 Contents
FSB 30 HE Natural Gas Potterton Gold FSB 30 HE No 592Installer Notification Guidelines Scheme Members onlyLegislation Important Installation, Commissioning, Service & RepairGas Safety Installation & Use Regulations Codes of Practice, most recent version should be usedContents Introduction DescriptionImportant Information General Layout Flow Temperature Thermistor RedPosition of Optional Integral Timer Wiring Layout Figs , 4, 5Boiler Operation Boiler OperationAll TRVs Shut Down ? Minute Anti-cycle Technical Data CAT I 2HIpxx Dimensions and Fixings System Details Water Circulating SystemsTreatment of Water Circulating Systems Low Head Installation PipeworkAir Vents System Controls & Wiring Sealed Systems Fig Site Requirements LocationCompartment Electrical Supply Clearances Figs &16Gas Supply 5mm Min 500mm Min For Servicing Purposes 390mmCondensate Drain General Condensate Disposal± 10 from vertical Site RequirementSink Blockage or restriction of the pipe into the drainFlue MINHorizontal Flue Systems Flue OptionsHorizontal Flue System Examples This bend is equivalent to 0.5 metreTotal equivalent length Vertical Flue System Examples Twin PipeTwin & Vertical Flue Systems 17.2 + 34.4 = 51.6 metresFlue Group B Flue AccessoriesCDS Flue Group PFor Vertical Flues For Vertical Flue Systems For Twin Flue SystemsFor Twin Flues Terminal Guard Fig Flue DimensionsFor Roof Terminals Flue Deflector aPlume Displacement Plume Displacement Kit P.D.KDetermining Permissible Lengths P.D.K General Fitting Notes P.D.K Min metres Min .3 metresThis section of the flue Must be horizontal Fig. H Installation Fitting the Standard Flue Flue Inner Flue Support BracketInner Flue Support Bracket Flue Elbow Gasket Flue Trim PointsMaking the Condensate Drain ConnectionMaking The Electrical Connections Cable Clamp Way Terminal BlockIntegral Programmer Green/Yellow Schematic Wiring DiagramElectrical Fuse 3.15 ATIllustrated Wiring Diagram PCBCommissioning the Boiler Commissioning the BoilerPriming the Condensate Pump Check the Operational Working Gas Inlet Pressure Fitting The Case Panels & Facia 13.2 ‘Benchmark’ ChecklistCompletion HandoverServicing the Boiler Annual ServicingEarth Combustion Box Door Panel Annual Servicing InspectionAir Box Door Panel Spark Sleeve InsulationLock Nut Service Drain Plug Central Insulation Panel Pipe may be removed to increase accessCracks/damage. Clean with a soft brush To it FigFlow Temperature Thermistor and Safety Thermostat Fig Changing ComponentsChanging Components & Preparation Drain the boiler see .1 paragraph 2 Condensate Pump Complete aClip Check operation of the pump See SectionChanging Components Spark and Sensing Electrodes Fig Condensate Trap Fig Injector Pipe FigGas Valve Fig Securing Nut Sensor Leads Condensate Trap Lock NutHeat Exchanger Manifold Assembly Heat ExchangerCombustion Box Door Panel Burner Support Bracket Burner Securing Screws Short Parts List Short Parts ListKey Description Fault Finding 240V at C ? 240V at a ?240V at B ? 240V at D ?System full of water ? Wires from inline Connector to PCB faultyViewed from Wire Entry end Replace Flow Switch Pump running ?Replace PCB Way Connector Lead from PCB to Gas Valve faulty Wiring from PCBRectify wiring Is there Gas at gas valve inlet ?Lights On Off Replace Stat Replace fan Lights Rectify wiring Viewed from Wire Entry end ‘C’ ‘D’ ‘B’ ‘A’YES Condensing Boilers only Service Record Potterton Brooks House, Coventry Road, Warwick. CV34 4LL Comp No 6/11