15.Four wood screws were supplied to temporarily attach the collar to the exterior wall of the building. However, you may have to substitute other types of screws depending on the construction material of the exterior wall.

20.Using a #22 drill bit, drill holes 180° apart at the connection point of the two 3” (76 mm) flue extensions. Secure with the two screws provided.

FIGURE 86.

16. Insert the vent cap into the vent collar assembly.

FIGURE 87.

17.The vent cap has four holes around the outer edge. Remove the four screws used to temporarily attach the collar to the exterior wall. Then secure the vent cap assembly with the vent collar assembly to the exterior wall using the same screws.

Note: Screws are supplied; however, substitution may be necessary depending on the exterior wall material.

FIGURE 88.

18.The remainder of the installation will be conducted indoors to complete the assembly process.

19.Collapse the 6” extension assembly as shown below. Install the O- ring end of the 3” (7.6 cm) extension approximately 11/4”(3.2 cm) into the end of the vent cap. If necessary, apply a soap solution to the O-ring to ease the assembly. Rotate the extension clockwise until the other end is locked to the studs on the elbow.

FIGURE89.

FIGURE 90.

21.Expand the 6” (152 mm) telescoping extension pipes to connect at the vent elbow.

FIGURE 91.

22.Push the vent collar from the elbow against the wall and secure with the four provided screws.

FIGURE 92.

23.Secure the 6” (152 mm) vent extension to the vent elbow with the two provided screws spacing them 180° apart.

FIGURE93.

Optional Vent Cap - Porcelain-Enameled

These supplementary installation instructions are applicable only if this direct vent water heater is provided with the alternate brown

22

Image 22
Contents Residential Direct Vent GAS Water Heaters Safe INSTALLATION, USE and Service Important DefinitionsGeneral Safety Table of Contents IntroductionTypical Installation GET to Know Your Water Heater GAS ModelsMixing Valve Usage Locating the NEW Water Heater Facts to Consider about the LocationCombustion Air and Ventilation Venting ClearancesOptional Wire Grill Flue ExtensionsVertical Height Extension Kit Chart #1Chart #2 Horizontal Extension KitCutting The Opening Through The Outside Wall ALL InstallationsStandard Vent Kit Installation #1 Water Heater AttitudePage Page Chart #3 GAL CAP BTU’s in 1000’s NAT./L.PPage Page Optional Horizontal Vent Kit Installation #3 Page Optional Vertical and Horizontal Vent Kit Installation #4 Through The Outside Wall. SeeChart #4 GAL CAP Collar Optional Vent Cap Porcelain-Enameled Page Page Installing the NEW Water Heater Water PipingTEMPERATURE-PRESSURE Relief Valve Valve and Pipe InsulationFilling the Water Heater GAS Piping Sediment Traps GAS Piping with Flexible ConnectorGAS Piping with ALL Black Iron Pipe to GAS Control Installation Checklist Before Lighting the PilotPage Start UP Conditions Temperature RegulationFor Your Information CondensateOperational Conditions GAS Control Valve & Burner Assembly Periodic MaintenanceBurner Cleaning Venting System InspectionAnode ROD Inspection TEMPERATURE-PRESSURE Relief Valve OperationHousekeeping DrainingDrain Valve Washer Replacement Leakage CheckpointsRepair Parts List Parts GAL. CAP KEY # Description BTU’s in 1000’s NAT/L.P 36/36 38/38 40/40 48/44 55 NATRepair Parts List This is a Repair Parts LIST, not a Packing List BTU’s in 1000’s NAT/L.P 36/36 38/38 40/40 48/44Troubleshooting Guidelines Page Page