American Power Conversion PD150G6F, PD150L6F manual Customizing and Updating the PDU

Models: PD150L6F PD150G6F

1 84
Download 84 pages 32.8 Kb
Page 61
Image 61

Customizing and Updating the PDU

4.At the front of the PDU, connect the power cord’s individual wires:

a.If you have branch current monitoring installed, route the phase conductor through a current sensor. If it is a three-phase cable, route the L1, L2, and L3 wires through a current sensor.

b.Connect the L1, L2, and L3 wires to the circuit breaker(s). The illustration below shows single pole breakers; however, you can also connect three-pole breakers.

c.Connect the neutral wire to the closest open termination point on the Neutral Bar (N).

d.Connect the ground wire to the closest open termination point on the Ground Bar (G).

N

G

You can configure your InfraStruXure system through the InfraStruXure Build-Out Tool to use 3, 20A, single-pole breakers to feed multi-circuit power cables supplying power to Caution L-N loads. However, one 3-pole, 20A circuit breaker must be used with any power cable

and Rack PDU that feeds L-L loads (NEC, NFPA 70).

150kW InfraStruXure PDU—Operation and Configuration

53

Page 61
Image 61
American Power Conversion PD150G6F, PD150L6F manual Customizing and Updating the PDU