APC 3000 Site Preparation UPS and XR, Installation Space Requirements, Space requirements

Models: 3000

1 58
Download 58 pages 30.91 Kb
Page 19
Image 19
Site Preparation (UPS and XR)

Site Preparation (UPS and XR)

Installation Space Requirements

Allow for enough working space behind the Enclosure for electrical work to be carried

out (e.g. if you want to connect an XR Enclosure at a later stage).

Clearance for 20.59in/523mm Enclosures

(B)

UPS

(A)

Conduit Box (F)

(C)

(D)

 

(G)

(E)

 

Space requirements

in

mm

 

 

 

Minimum clearance above Enclosure (A)

20

508

 

 

 

Enclosure depth (B)

33.62

854

 

 

 

Enclosure width (C)

20.59

523

 

 

 

Minimum free rear space for ventilation* (D)

4

100

 

 

 

Minimum front clearance (E)

39.37

1000

 

 

 

Conduit Box, depth (F)

3.46

88

 

 

 

No side clearance required (add width of Enclosure Stabilizing

0

0

Brackets for floor anchoring if applicable)*

 

 

 

 

 

Stabilizing Bracket width

3.34

85

 

 

 

Total installation depth, inclusive of Front Panel, Conduit Box

80.39

2042

and minimum front and rear clearances (G)

 

 

 

 

 

*) All physical installations must comply with NEC 110.26.

AIS® 3000 10-30kVA, 208V, Site Preparation and Installation Manual – 990-1957

11

Page 19
Image 19
APC 3000 Site Preparation UPS and XR, Installation Space Requirements, Clearance for 20.59in/523mm Enclosures