APC 3000 installation manual Electrical Installation - Input/Output Wiring - Dual Mains

Models: 3000

1 58
Download 58 pages 30.91 Kb
Page 43
Image 43
Electrical Installation – Input/Output Wiring – Dual Mains

Electrical Installation – Input/Output Wiring – Dual Mains

Punch 3 holes in the Conduit Box bottom to fit the size of the conduit pipes.

Attach the Conduit Box bottom to the Enclosure, using (4) M4x13 screws.

Install conduit pipes in the Conduit Box bottom.

Run cables through the conduit pipes and the bottom of the Conduit Box. Guide the cables up into the input/output area.

Install the top part of the Conduit Box to the Enclosure.

Remove the (2) M6x12 screws from Brackets A, B, and C and remove all 3 brackets.

Input Manual background

Neutral Manual background Bypass Manual background

Output Manual background

Ground Manual background

L1 Manual background

L2 Manual backgroundManual backgroundManual background L3 Manual backgroundManual background

Manual backgroundManual backgroundN Manual backgroundManual backgroundManual backgroundManual background N

L1

L2

L3

L1 Manual backgroundManual background

L2

 

L3

Batt+

N

 

 

Batt-

Plate covering cable termination area



Attach the input cable lugs to input busbars L1, L2, L3, using the provided hex screws. Attach the bypass cable lugs to L1, L2, L3 bypass busbars, using the provided hex screws. Attach the output cable lugs to the L1, L2, L3 output busbars and attach, using the provided hex screws.

Attach N x 3 where shown., using the provided hex screws.

Attach Ground x 3 where shown.

Reinstall the Plate, following reversed deinstallation procedures (described in a previous step).

AIS® 3000 10-30kVA, 208V, Site Preparation and Installation Manual – 990-1957

35

Page 43
Image 43
APC 3000 installation manual Electrical Installation - Input/Output Wiring - Dual Mains