Rev. 3.02 - 82 -
SRP-270
8-8-2-5 Main assembling - #2
Name of Parts Method and Procedure
GEAR REDUCTION A
GEAR REDUCTION B
RIBBON FEEDER ASSY
GEAR REDUCTION “C”
LEVER RIBBON FEED ASSY
WASHER (ø 2.6*5*0.5, 2EA)
MAIN PCB ASSY
FPC CONNECTOR
SCREW MACHINE (M3*4)
CARRIAGE HEAD ASSY
BELT SYNCHRONUOS
SPRING LEVER TENSION BELT
1. Set FRAME MAIN on the JIG.
2. Set GEAR REDUCTION A, GEAR REDUCTION B,
RIBBON FEEDER ASSY and GEAR REDUCTION "C"
onto SHAFT sequentially. Grease teeth and upper face of
RIBBON FEED ASSY.
3. Insert LEVER RIBBON FEED ASSY and WASHER.
4. Attach FPC CONNECTOR to MAIN PCB ASSY. Next,
plug SOLENOID WIRE (block) in connecter 2p. And then, set
it to M/F and tighten two SCREW MACHINE.
5. Insert BELT SYNCHRONUOS into CARRIAGE HEAD
ASSY, and then, belt up round PULLEY and GEAR PULLEY.
6. Hoot SPRING LEVER TENSION BELT.
<Check Point>
Check the tear of FPC.