2-3
Cisco AS5350 Universal Gateway Chassis Installation Guide
78-10754-03 0A
Chapter2 Preparing to Install the Cisco AS5350 Chassis Required Tools and Equipment
safely ground unwanted ESD voltages. To guard against ESD damage and shocks, the wrist strap and
cord must operate properly. If no wrist strap is available, ground yourself by touching the metal part of
the chassis.
Caution For safety, periodically check the r esistance value of the antistatic st rap, which should be between 1 an d
10 megohm (Mohm).
Required Tools and Equipment
The following items are inc lu de d with the universal gateway:
19- and 24-inch rack-mount kits
Rubber feet for desktop installatio n
RJ-45-to-DB-9 female DTE adapter (labeled TERMINAL)
RJ-45-to-DB-25 female DTE adapter (lab eled TER MINAL)
RJ-45-to-DB-25 male DCE adapter (labeled MODEM)
RJ-45-to-RJ-45 rollover console cable
ESD-preventive wrist strap
Nylon cable tie
Cable tie holder
Grounding lug
You might need the following equipment, which is not included:
Straight-through RJ-45-to-RJ-45 cable for an Ethernet connection
Up to two straight-through RJ-45-to-RJ-45 cables for T1 connections
Up to two E1 cables for E1 conn ec tio n s
Ethernet hub or PC with a network interface card for Ethernet LAN connections
PC running terminal emulation so f tw are f o r l o cal ad m ini strative access
Modem for remote administrative access
Preparing to Connect to a Network
When you set up your universal gateway, consider distance limitations and potential electromagnetic
interference (EMI) as defined by th e Ele ctronic Industries Association (EIA).
Warning
Hazardous network voltages are present in WAN ports regardless of whether power to the router is
OFF or ON. To avoid electric shock, use caution when working near WAN ports. When detaching
cables, detach the end away from the router first. To see translations of the warnings that appear in
the publication, refer to the Regulatory Compliance and Safety Information document that
accompanied this device.