8 Vent Clearances and Framing

A. Pipe Clearances to Combustibles

Refer to Fiture 8.1.

WARNING! Risk of Fire! Maintain air space clearance to vent. DO NOT pack insulation or other combustibles:

Between ceiling firestops

Between wall shield firestops

Around vent system

Failure to keep insulation or other material away from vent pipe may cause over heating and fire.

B. Wall Penetration Framing

Refer to Figure 8.2.

Combustible Wall Penetration

Whenever a combustible wall is penetrated, you must frame a hole for the wall shield firestop(s). The wall shield firestop maintains minimum clearances and prevents cold air infiltration.

The opening must be framed on all four sides using the same size framing materials as those used in the wall construction.

3 in.

 

 

(76 mm)

 

Air space clearance to

 

 

bottom and sides of

 

 

horizontal pipe must be

 

 

at least 1 in. (25 mm)

Cement

 

 

Board

 

 

Steel Stud

 

No combustible

Assembly

 

framing to be

 

 

located within

 

 

shaded area.

 

WALL

1-1/2 in. (13 mm)

 

minimum to

 

 

 

 

perpendicular

 

 

wall.

Figure 8.1 Horizontal Venting Clearances To Combustible Materi- als

• A wall shield firestop is required on one side only on

 

 

 

 

interior walls. If your local inspector requires a wall shield

 

 

 

 

firestop on both sides, then both wall shield firestops

 

 

10 in.

 

must have a heat shield attached to them.

 

 

(254 mm)

 

• See Section 10.I. for information for regarding the

12 in.

 

Vent Framing Hole

installation of a horizontal termination cap.

 

 

 

(305 mm)

 

 

 

 

 

 

 

Noncombustible Wall Penetration

 

 

 

 

If the hole being penetrated is surrounded by noncombus-

 

 

 

 

tible materials such as concrete, a hole with diameter one

 

 

 

 

inch greater than the pipe is acceptable.

 

 

 

 

Whenever a noncombustible wall is penetrated, the wall

 

 

Framing should be

 

shield firestop is only required on one side and no heat

 

 

 

 

 

constructed of

 

shield is necessary.

 

 

2x4 lumber.

 

 

 

 

The center of the

102 1/2 in.

 

 

 

framing hole is

(2604 mm)

 

 

 

1 in. (25 mm) above

from center of

 

 

 

the center of horizontal

pipe to bottom

 

 

 

vent pipe.

of appliance

 

 

 

 

6 in.

 

 

 

 

(152 mm)

 

Figure 8.2

Wall Penetration

 

Heat & Glo • LUX60 • 4062-116 • Rev. G • 4/11

 