Setting up and Installing the Interconnect Switch

7.Simultaneously pull both slate blue ejector levers toward the rear of the server blade enclosure (2).

IMPORTANT: Slate blue indicates internal touch point components.

8. Pull the existing interconnect tray out of the server blade enclosure.

Figure 2-7: Inserting the new interconnect tray and engaging the interconnect tray levers

9.Insert the new interconnect tray into the server blade enclosure (1).

10.Simultaneously rotate both ejector levers to the locked position (2).

Figure 2-8: Installing a hot-plug power supply

11.Install the hot-plug power supplies (1).

12.Push the power supply handles to the closed position (2).

13.Download the switch configuration file from the TFTP server. Refer to the “Downloading Configuration File on a TFTP Server” section in the management interface reference guides. If no configuration file is available, reconfigure the switch modules.

HP ProLiant BL e-Class C-GbE Interconnect Switch User Guide

2-5