Setting up and Installing the Interconnect Switch

7. Pull the patch panel tray out of the server blade enclosure (3).

Figure 2-11: Inserting the interconnect tray and engaging the interconnect tray levers

8.Insert the interconnect tray into the server blade enclosure (1).

9.Simultaneously rotate both ejector levers to the locked position (2).

Figure 2-12: Installing a hot-plug power supply

10.Install the hot-plug power supplies (1).

11.Push the power supply handles to the closed position (2).

HP ProLiant BL e-Class C-GbE Interconnect Switch User Guide