Setting up and Installing the Interconnect Switch

Figure 2-15: Connecting the power cables

3.Install the power cords. The server blade enclosure and interconnect switch power up as soon as power is applied to the enclosure.

CAUTION: Because the server blade enclosure uses both power supplies for power redundancy and proper cooling, be sure that both power cords are connected at all times.

Figure 2-16: Routing the cables

4.Bundle the network and power cables together and route them to the outer edge of the rack.

2-12

HP ProLiant BL e-Class C-GbE Interconnect Switch User Guide